As a systems analyst, you will probably
be called on to produce a number of estimates for
your project. Indeed, you may be solely responsible
for producing these estimates in some cases; in other
cases, your project manager may ask you to develop
estimates for his or her use.
What kind of things need to be estimated in a systems
development project? This will vary from project to
project, but typically the major things that need
to be estimated are:
-
People
resources. How many programmers, systems analysts,
database designers, telecommunications experts,
user representatives, and other categories of people
will be required for the project?
-
Schedule.
How long will the project take? How much time can
be expected for each of the typical phases of the
project (e.g., systems analysis, design, programming,
testing, etc.)?
-
Staff
scheduling. In addition to knowing how many
people the project will require, we need to know
when they will be required. If the project requires
ten programmers, will all ten be needed at the same
time?
-
Budget.
How much money will it cost to develop the system?
The major cost is likely to be the salaries paid
to the development staff, and this can usually be
computed directly once the staffing and staff scheduling
is known. But, of course, there are other costs
associated with a project; these are detailed in
Appendix C.
Keep in mind that you will generally
have to make these estimates more than once. A set
of estimates will generally be made in the early stages
of a project (e.g., during the feasibility study),
but they may need to be made many times, as users
and management explore the ramifications of different
trade-offs. One obvious example of this is the trade-off
between time and functionality (e.g., the project
manager might say to the user, “I’m pretty
sure we can deliver the system to you by January 1st
if you leave out functions X, Y, and Z.”); another
example is the trade-off between time and people (e.g.,
the user might say to the project manager, “If
you had three more programmers, would you be able
to get the system done in time?”). It may take
several iterations before the project team, management,
and the user community have reached an acceptable
compromise. [1]

B.2 ESTIMATING DANGERS
We have a great deal of common experience in the area
of estimating; just think of all the situations typified
by the question, “How long do you think it will
take to drive to your grandmother’s house?”
And we are all intuitively familiar with the concept
of an optimistic estimate and a pessimistic estimate.
But estimating a systems development project is somewhat
different, because (1) the scope of work is much larger
and more complex, and (2) the consequences of an estimating
error are usually much more severe than that of being
half an hour late to your grandmother’s house.
[2] There are a number of common
problems that you should be aware of before you begin
calculating estimated budgets, schedules, and resource
requirements:
-
The difference
between estimating and negotiating
-
The wide
variation in technician skills
-
The danger
of estimating your own work
-
The lack
of an estimating database
-
Management’s
insistence on premature, detailed estimates
-
An industry-wide
difficulty of measuring the unit of work
-
Estimates
based on assumptions of unpaid overtime
Depending on your seniority in your
project, and your clout with management and users,
you may be able to prevent some of these problems
from becoming serious. But even if you are a junior
systems analyst on the project, you should be aware
of the estimating problems, for they can ultimately
determine the success or failure of your project.
All of these problems — which do lead to faulty
estimates in many projects — underscore the
need for formally establishing a “triage”
approach when the requirements for the project are
identified. Even if the initial estimate is reasonably
accurate, problems may be encountered in the middle
of the project that will make it difficult to implement
all of the requirements by the time the deadline arrives.
But more commonly, the estimate turns out to have
been inaccurate from the very beginning; thus, it’s
essential that the end-user and the project team understand
which features/requirements are essential (sometimes
known as “must-do” requirements), which
ones are important (i.e., “should do”),
and which ones are optional (i.e., “could do”).
We will discuss each of the problems in more detail
next.
B.2.1 The Difference Between
Estimating and Negotiating
There is often a great deal of negotiation at the
beginning of a project (and often throughout the development
phase of the project!). This is normal, because the
user community often has little understanding of the
amount of work involved in a complex information system
and will thus “ask for the moon,” that
is, an enormous amount of functionality in an absurdly
small amount of time, and for little or no money.
Meanwhile, the project manager is faced with limited
staff and a limited budget; hence, she or he needs
to work with the users to help them see what trade-offs
are possible.
But this negotiating process, so necessary and so
common in systems development projects, must not be
confused with estimating. What you must avoid is the
conversation between user and systems analyst (or
whoever does the estimating) that goes like this:
User: “So,
how long is it going to take you to build the XYZ
system?”
Analyst:
“Well, it looks like we’ll have it finished
by April 1st.”
User: “That’s
not good enough. We need it by January 1st.”
without a willingness to discuss
other trade-offs in functionality or resources. [3]
This is sometimes followed by an appeal by the user
to the project team’s sense of devotion, duty,
and patriotism, which we will discuss as a separate
problem in Section B.1.8. [4]
In some cases, this situation simply reflects a lack
of understanding on the part of the user; it can usually
be corrected by a careful explanation of the activities
involved in developing a system. In other cases, though,
it reflects the user’s overall approach, his
business “paradigm,” for dealing with
people and organizations that provide him with products
and services. To the typical user, you see, the internal
data processing organization is not that much different
from an external vendor; negotiating, in an attempt
to squeeze the price down or cut the schedule back
a few months, is a very natural thing to do. And it
is a reasonable thing to do (from his point of view)
if the person or organization providing that service
has a profit margin that can be cut down through skillful
negotiation.
Even in the case of an internal data processing organization,
negotiating (without accepting any trade-offs in functionality,
resources, budget or schedule) may be reasonable if
your estimates include a margin for error (otherwise
known as a cushion or a contingency factor) that the
user thinks is unreasonably large. But if you have
provided careful, realistic estimates, and the user
negotiates you down to a smaller staff, smaller budget,
and tighter schedule, then your project has entered
the realm of heavy-duty politics for which the techniques
and tools discussed in this book probably won't help
much. The time may have come to update your résumé.
Alternatively, if you decide to participate in the
project despite having been negotiated into an unrealistic
deadline, budget, or resource allocation, you should
realize that you are probably going to experience
what is commonly known as a “death-march”
project. As the name implies, such projects often
involve large amounts of overtime, leading to a certain
degree of stress and exhaustion. However, there are
a number of things that the project manager and team
can do to maximize their chances of success in such
projects; for more details, see [Yourdon, 1997].
B.2.2 The Wide Variation
in Technician Skills
It is common to make estimates of the work to be done
based on average talent (i.e., the typical programmer
or systems analyst, who can write 15 lines of code,
or draw four DFD bubbles, in an average day). It’s
important to keep in mind that numerous studies over
the past 20 years have documented an order of magnitude
difference between talented professionals and mediocre
professionals in the field. [5] If
your project has a group of so-called super programmers,
you may drastically overestimate the amount of time
and money that will be required to finish the project.
Of more concern is the fact that a project team of
dullards may cause your project to miss its schedule
and exceed its budget by a substantial amount.
One major problem in this area is that the actual
performance of experienced practitioners does not
correlate strongly with most standard programming
aptitude tests. Hence, you must base your estimates
on each person’s reputation or previous work
experience, or you must simply assume that everyone
on the project is average. Since most organizations
don’t keep careful, detailed records on the
productivity of each person in a systems development
environment, it will be very difficult for you to
obtain documented evidence that you can trust. All
you can do is make your best judgment and then modify
the estimates, as appropriate, during the course of
the project.
B.2.3 The Danger of Estimating
Your Own Work
One of the worst mistakes that you can make is to
estimate your own work; it is almost as bad to use
the estimate of any one single person, since that
person’s judgment may be affected by a number
of factors.
If you estimate your own work, you are very likely
to fall prey to one or more of the following myths:
-
“I’m
better than most of the other people around here,
and I’m sure I can finish the project much
sooner.” It’s very common to overestimate
one’s ability. When estimating someone else’s
ability, you tend to be conservative; when estimating
your own, you tend to be optimistic.
-
“I
know that the boss needs this project done real
fast, and I really want to help her out.”
In most cases, this is an altruistic feeling; it’s
quite natural to want to help your boss succeed.
But it can cloud your judgment about the actual
amount of time required to get the project finished.
In the worst case, optimistic estimates are made
in an effort to impress your boss (keep in mind
that he’s doing the same thing to his boss,
and his boss is doing the same thing to his boss,
etc.) so that you can get that next raise or promotion.
If you know what you’re doing and are able
to accept the risk, fine; [6] but
keep in mind that you’re playing with fire.
-
“I’m
willing to work hard to get this project done on
time.” The willingness to work overtime
is commendable, but it is dangerous, as suggested
earlier. Also, keep in mind that the commitment
to put in long hours is often made in a moment of
excitement at the beginning of the project; six
months later, it may not seem like such a good idea.
For more details on the characteristics of such
“death-march” projects, and the strategies
for surviving them, see [Yourdon, 1997].
-
“I’ve
worked on systems like this before; this will be
a piece of cake.” Well, maybe, if indeed
you have worked on a project exactly like this one
or very close indeed. However, there is a tendency
at the beginning of a project to see superficial
similarities with previous projects and to optimistically
assume that you’ll be able to do the new project
even more quickly. You’re likely to find that
the new project is actually rather different, once
you get into the details; and you’re likely
to forget all those problems you encountered in
the last project.
For these reasons, it’s very
important that estimates be carried out by someone
other than the person responsible for the work. It’s
also highly desirable if one does not have an estimating
database (discussed in Section B.1.4) or a computerized
estimating package (discussed in Section B.4) to obtain
estimates from more than one person. At the very least,
get estimates from three people; this will give you
a best case and worst case estimate, along with an
in-between estimate.
B.2.4 The Lack of an Estimating
Database
When faced with a new project, one would like to use
statistics from a hundred similar projects in order
to produce accurate estimates. Some consulting firms
and software houses are able to do this: when asked
to estimate the time and cost for, say, an order entry
system, they can say, “Well, this is almost
exactly the same as the last 137 order entry systems
we’ve built, so it should take X person-months,
Y dollars, and Z people.”
Even within your own organization, it’s possible
that there have been 137 order entry systems developed
over the past decade or two. But this doesn’t
necessarily mean that it will be easy to estimate
the budget or schedule for the 138th order entry system;
if careful records have not been kept, all you can
go on is hearsay and rumor. For a typical data processing
organization, which acts as an internal service organization,
without having to worry about profit/loss figures
or cash flow considerations, there is no real incentive
to keep such careful records.
Some large data processing organizations are beginning
to change this attitude and have begun developing
large, detailed databases that can be used to generate
much more accurate estimates for future projects.
And some consulting firms specializing in this area
have developed databases of literally thousands of
projects; these are usually used to provide parameters
in the computerized estimating models discussed in
Section B.4.
In the meantime, there is a significant likelihood
that you will be faced with a one-of-a-kind estimate.
You should certainly look for other, similar projects
in your organization; but be aware that you may be
in a situation analogous to the architect who was
asked how long it would take build an underground
house in a swamp.
B.2.5 Management’s
Insistence on Premature Detailed Estimates
As a general rule, it is almost impossible to produce
detailed estimates of costs, time, and resource requirements
for a project until a considerable amount of detailed
systems analysis and design have been done. After
all, how can you tell the user how much a system will
cost if you don’t know what the user wants?
Nevertheless, there is often great pressure from both
users and management to produce an estimate, which
is presumed by both of those parties to be an accurate,
detailed estimate, at a very early stage in the project.
Why? Simply because they need to make a go/no-go decision
to invest the time, money, and people required to
build the system.
Indeed, in the worst case the schedule and deadline
are determined before a project manager has been assigned,
before anyone has done any thinking about budgets
or personnel allocations, and before anyone has a
clue about the detailed requirements for the system.
You might well ask: how could a rational organization
allow such a thing to occur? The answer is quite simple:
external pressures. If the government suddenly announces
new tax laws, or new reporting requirements for safety
codes or employee pension plans, there is likely to
be a deadline associated with those laws and requirements.
If a competitor suddenly introduces a hot new product
that threatens the success of the organization’s
existing products, senior management may decree a
deadline for creating a competitive response even
before they worry about the other details. In other
words, situations like this might not seem reasonable,
but they do happen, and for very “real”
reasons.
This demand for an early estimate is quite understandable;
the only thing that is not realistic is the assumption
that an early estimate can be detailed or accurate.
It’s more appropriate to give management a series
of estimates throughout the project, with each one
being progressively more detailed and more accurate.
Thus, if the project team is developing a system for
an application they are fairly familiar with, they
might provide the following series of estimates:
-
At the
end of the survey or feasibility study: an estimate
that may vary by plus or minus 50%. That is, the
project team might tell management that the system
will take one year and cost $200,000, plus or minus
50%. Management should thus realize the possibility
of the project taking 18 months and costing as much
as $300,000.
-
At the
end of the analysis phase: an estimate that may
vary by ± 25%.
-
At the
end of the design phase: a revised estimate that
may vary by ± 10%.
-
At the
end of the programming phase (when testing remains
to be done): a final estimate that should not vary
by more than ± 5%.
B.2.6 An Industry-Wide Difficulty
of Measuring the Unit of Work
Many industries have standard ways of measuring the
amount of work to be done in a project. Someone building
a house, for example, might measure the work in terms
of the number of bricks to be laid or the number of
rooms to be built. But in the field of systems development,
there is still no agreed-upon way of measuring the
unit of work to be done.
The most common method is to measure the number of
program statements to be written, otherwise known
as lines of code. Thus, on some projects, you will
see references to KLOC, which stands for kilo lines
of code. But there are many problems with lines of
code as a measure of the unit of work:
-
Do comments
in a computer program count as a line of code?
-
Do we
count only the code that is delivered to the user,
or do we also count code that is written for testing,
utility programs, and other support activities during
the project? (And on a larger scale, do we count
the code associated with canceled projects in an
attempt to measure enterprise productivity?)
-
What
if the programmer has written more than one program
statement on a single line of a program listing?
And what about the complex statement that takes
more than one line?
-
Most
important, how do we deal with the fact that some
programmers will take more lines of code to accomplish
the same function than other programmers? As we
saw in Section B.1.2, this can represent an order
of magnitude variation!
As Capers Jones points out in Applied
Software Measurement ([Jones, 1997]) different ways
of measuring the unit of work can distort the reported
productivity results by two orders of magnitude; perhaps
that’s why some programmers can claim to be
10 times or even 100 times more productive than their
colleagues! Because of these problems, some organizations
are now beginning to use function points as the unit
of work; this corresponds roughly to the bottom-level
atomic bubbles in a DFD.[7]
B.2.7 Estimates Based on
Assumptions of Unpaid Overtime
As mentioned earlier, users and project managers may
react to scheduling conflicts by suggesting, implicitly
or explicitly, that the project team put in extra
hours, work on weekends, skip holidays, and postpone
vacations. This is usually accompanied with appeals
to the loyalty, professionalism, dedication, devotion,
pride, honor, and patriotism of the project participants.
I’ll leave it to you to decide whether a willingness
to work extra hours is a necessary attribute of patriotism.
In some organizations, this may be the case: every
project may be organized in such a way that it will
only succeed if the project team regularly puts in
an 80-hour week. And some projects (e.g., the NASA
Apollo project that put the first men on the moon
in the late 1960s) may be so exhilarating that everyone
will be more than happy to sign up for the extra work
required. And it’s not uncommon to find that
a project that appeared to be under control falls
behind schedule during the last month, requiring a
few weeks of late evenings and weekends.
But you have to remember that working is like running:
you can sprint at top speed for a hundred yards, but
you can’t sprint at top speed for a 26-mile
marathon. Similarly, you can work 14-hour days for
a few weeks, but it’s unrealistic, in most cases,
to assume that you can work 14-hour days for a 3-year
project. People with spouses (spice?), children, or
other outside interests will simply refuse to continue
working such hours after a few months; if necessary,
they’ll quit and find another job. Young, single
people may be more willing to devote their entire
waking lives (as well as their dreams) to the project,
especially if they feel it will help advance their
career or their knowledge of the profession.
Even if members of the staff are willing to work 14-hour
days, there is no guarantee that they will be effective
at their work. This is especially true if the overtime
work continues for a period of several months: the
long evening hours are often unproductive, and one
usually finds that more errors are created as people
do their work in an exhausted, frazzled state of mind.
There’s a more subtle version of this problem
in many organizations: overtime work on the part of
professional staff members throughout the organization
(not just IT) is allowed, encouraged, and even expected
— but not measured. [8] The
rationale is simple: since professional “knowledge
workers” are not paid for such work (at least
not in most North American and Western European countries),
there is no need to measure it. Indeed, to do so is
an embarrassing reminder to management that either
(a) they created such poor estimates of the project
that they had no alternative but to ask their staff
to work long hours, or (b) they deliberately created
a “slave labor” environment to cut labor
costs. Whether or not one agrees with the ethics of
such management practices, it’s still a bad
idea not to measure the overtime — for it creates
a false impression of the “true” productivity
(e.g., lines of code per person-day), schedule, and
budget.
B.3 ESTIMATING GUIDELINES
There are four important guidelines to keep in mind
when you develop estimates for the amount of work
to be done in a systems development project:
-
Make the
estimating units as small as possible.
-
Make the
units of work as independent as possible.
-
Take into
account the communication factor.
-
Distinguish
between new work and borrowed work.
-
Be aware
of the impact of time-delays and feedback loops
between various activities in the project life cycle.
These are discussed next.
B.3.1 Make the Estimating
Units as Small as Possible
This should be an obvious suggestion, but it is not
followed as often as you might think; it also has
some pitfalls, as we shall see. But, in general, it’s
much better to estimate the budget and schedule for
a one-week unit of work than it is to estimate a “man-millennium.”
[9] Large projects have large complexities;
if you try to estimate the amount of work involved,
you are almost certain to make major errors. It makes
much more sense to base your estimates on small amounts
of work.
This implies, of course, that the overall project
has been broken down into small units of work. This
will normally happen quite naturally as a result of
structured analysis, structured design, and structured
programming; unfortunately, as discussed in Section
B.1.5, you may be required to provide a detailed estimate
of budget and resource requirements before this detailed
work-breakdown has taken place. There is no magic
solution to this problem; all you can do is try to
impress upon your managers and the users that a detailed,
accurate estimate requires some initial effort to
identify the units of work to be done.
But how small should the units of work be? Some organizations
measure work in units of one month; however, this
seems too large — projects can get seriously
out of control in the span of one month. It is perhaps
more reasonable to measure work in units of one week;
as one veteran project manager said to me, “Nothing
useful ever gets done in less than a week.”
Perhaps the most common unit of work, though, is a
day; this fits nicely with the way we organize our
work life. A few organizations actually measure their
work in units of an hour; while there are indeed many
activities that take an hour or less (e.g., defining
a single data element in the data dictionary), it
seems too microscopic a unit to work with.
B.3.2 Make the Units of Work
as Independent as Possible
A problem that has plagued many attempts at estimating
is the interaction, or coupling, between one piece
of work and another. If a system is divided into pieces
with many, many interactions, then the total amount
of work to develop the system will be far more than
the linear sum of the work for each piece. If a change
is made to piece 13, for example, the change may cause
problems in piece 14, and a change to 14 could result
in changes being made to 15, and so on. This ripple
effect has wreaked havoc in many projects.
The solution is to divide the system into small, independent
pieces that are only loosely coupled to other pieces.
This requires careful work; we discussed it in Chapter
20 as the major rationale for grouping low-level bubbles
in the preliminary behavioral model into higher-level
aggregates. The notion of modular independence is
also important during the design phase of the project;
we discussed this in Chapter 22.
B.3.3 Take into Account the
Communication Factor
Even in a project where all the modules are independent
of one another, people have to talk to one another.
If the project is carried out by one individual, then
the only communications required are those that take
place with the user (and perhaps some discussions
with management). But a typical project has many systems
analysts, designers, database specialists, and programmers;
even worse, some of these people may work in different
companies or even speak different languages.
Thus, your estimates will have to include some time
for communication between all the project personnel.
This communication will take the form of meetings,
memos, telephone conversations, and so forth. Keep
in mind also that the amount of communication increases
sharply as the size of the project team increases:
the number of communication paths between team members
increases as the factorial of the number of individuals.
B.3.4 Distinguish Between
New Work and Borrowed Work
If the project team is lucky, it will be able to make
use of work that was done on previous projects; most
often, this takes the form of modules in a common
software library. [10] However, you
should not assume that the reusable modules are free;
it will take some amount of work to (1) find them,
(2) investigate them to see if they perform the desired
function, and (3) learn enough about them to understand
how to use them. It’s more appropriate to estimate
that the borrowed modules will require some fraction
(perhaps 25%, perhaps as low as 10%) of the work that
would have been necessary to develop the modules from
the beginning.
B.3.5 Be Aware of Time Delays
and Feedback Loops
In Chapter 6, we saw several examples of typical “project
life cycles” for systems development; they consist
of a network of activities, with the output from one
activity becoming input to the next. However, there
are two common oversimplifications that project teams
make when using these life-cycle models as the basis
for their estimates:
They assume that the “transition” from
activity N to activity N+1 is instantaneous. But in
the “real world,” that may not be true;
there are often “hidden” delays that prevent
activity N+1 from getting started. For example, activity
N might produce a set of data flow diagrams and other
documents, which must be sent via “snail-mail”
to a different group carrying out the design and implementation.
If the post office takes a week to deliver the snail-mail,
then activity N+1 has been delayed for a week. Or,
equally common: the technical team has finished producing
the output for activity N, but is not permitted to
send it onward until it has been officially “approved”
by the manager of the team that carried out the technical
work. Unfortunately, the manager is away on vacation
for two weeks, so nothing happens until he or she
returns — and, in particular, activity N+1 doesn’t
begin.
They assume that work always flows “forward”
from activity N to activity N+1 to activity N+2, etc.
But sometimes there are feedback loops — i.e.,
work flows “backward” from activity N+1
back to activity N because of problems, misunderstandings,
or changes in the business environment. For example,
when the systems analysis activity is finished, the
output (dataflow diagrams, etc.) is sent to the design
activity; but if the designers discover analysis-related
defects, then they must send the materials back to
the analysis group for re-work. Re-work (and thus
a feedback loop) is also common when the testing activity
discovers bugs that require re-programming effort.
Models that emphasize time-delays and feedback looks
are often referred to as systems dynamics models;
thus, the ideal “estimating model” would
be more complex and sophisticated than a simple mathematical
formula. Indeed, system dynamics models of the software
development process have been developed, though they
are not widely used; for more details, see [Abdel-Hamid
and Madnick, 1991].
B.4 FORMULAS FOR ESTIMATING
During the past 20 years, the systems development
industry has invested an enormous amount of time and
effort developing models, or formulas, to help predict
the time, resources, and cost of a system. Some of
these models are now in widespread use; perhaps the
best known model is the COCOMO model developed by
Barry Boehm at TRW. [11] But as Tom
DeMarco points out in Controlling Software Projects.
There are no transportable cost models. If you wait
for someone elsewhere to develop a set of formulas
that you can use for cost forecasting in your own
shop, you will probably wait forever. Much of our
industry concluded, upon realizing this fact, that
cost modeling was therefore irrelevant. I think that
was the wrong conclusion. If locally developed cost
models can be used to improve the precision of the
cost-forecasting process, and if the improvement is
worth the cost of developing the models, then the
concept is viable.
However, it is interesting to see some of the formulas
used in other organizations; if nothing else, they
will give you a starting point for developing your
own formulas. Some of the formulas involve as many
as 40 factors or parameters; but, as we will see,
some involve only one parameter.
B.4.1 Formulas for Estimating
Work Time
Three common formulas for estimating the effort (described
in person-months) are based on lines of code. Walston
and Felix developed a model at IBM (see [Walston and
Felix, 1977]), based on observations of some sixty
projects, which is expressed as
E = 5.2 *
L0.91
where E was measured in person-months, and L was
measured in thousands of lines of code.
Similarly, Bailey and Basili developed a formula based
on 19 projects; it is expressed as
E = 3.4 +
0.72 * DL1.17 plus or minus 25%
where effort was measured, once again,
in person-months, and DL is thousands of lines of
delivered code; see [Bailey and Basili, 1983].
Finally, Barry Boehm’s COCOMO model has an effort
formula for three different types of system: organic
systems, semidetached systems, and embedded systems:
E = 2.4 *
KDSI1.05 (organic systems)
E = 3.0 *
KDSI1.12 (semidetached systems)
E = 3.6 *
KDSI1.20 (embedded systems)
where KDSI represents Òkilo delivered source
instructions; see [Boehm, 1981] for details.
B.4.2 Formulas for Estimating
Time
Once you have developed an estimate of the amount
of work to be done, you might think that it’s
easy to estimate the length of time that the project
will take. After all, if you have a project estimated
at 10 person-months of work, and 5 people are available,
then it should take 2 calendar months to finish the
project. But what if only 2 people are available?
Does the project then take 5 calendar months?
In general, what we are concerned with here is the
trade-off between time and people. Many years of painful
experience have taught us that the trade-off is not
a simple one: doubling the number of people on a project
does not necessarily cut the duration of the project
in half. Indeed, Fred Brooks, the architect of the
original OS/360 operating system, coined the phrase,
“Adding more people to a late software project
just makes it later.” There are two reasons
for this: (1) adding more people increases the required
communication between team members, which reduces
productivity, and (2) some work in the project is
indivisible; it can only be done by one person and
adding more people simply won’t help.
While this is a useful concept, it does not tell us
specifically how many people a project will need nor
how long it will take. This area has also been the
subject of research; Barry Boehm found, for example,
that the calendar time for a project could be expressed
by the following formula:
T = 2.5 *
E0.33
where E is the effort of the project
measured in person-months; see [Boehm, 1981] for details.
Studies have also been made of the optimal “manpower
loading” for a project; the three best known
formulas are based on the work of Norden, Putnam,
and Parr; see [Norden, 1963], [Putnam and Fitzsimmons,
1979] and [Parr, 1980]. Norden was the first to find
that project staffing follows a curve similar to the
one shown in Figure B.1.
The chart is often known as a Rayleigh distribution,
based on the mathematical formula for the curve. Putnam
provided a formula describing the number of people
required on the project as a function of calendar
time:
People(t)
= 2K * a * t * exp(-at2 )
where K is the total effort of the
project (expressed in people-months), and a is an
acceleration factor that establishes the initial slope
of the curve. (Note that K represents the total area
under the curve.)
An alternative model was developed by Parr [Parr,
1980]; while the overall shape looks similar to Figure
B.1, it estimates a higher amount of staffing in the
early phases of the project. The Parr model is described
by the following formula:
People(t)
= 1/4 sech2 ((at + c)/2)
B.5 COMPUTERIZED ESTIMATING
MODELS
The idea of using formulas with exponentials and hyperbolic
secants is probably not very appealing; you can be
sure that most veteran systems analysts have long
since forgotten what a hyperbolic secant is and have
no idea how to compute an exponential! But it’s
not necessary to remember any of the formulas, nor
is it necessary to carry out any of the calculations
by hand. There are now many computerized project estimating
packages available; most run on PCs, and many of them
utilize Boehm’s COCOMO model, as well as the
Putnam model described above. Some can also incorporate
the PERT charts and GANTT charts discussed in Chapter
16. Among the more popular estimating products are
CHECKPOINT, from SPR (www.spr.com); SLIM, from Quantitative
Systems Management (www.qsm.com); and OnYourMark,
from Omni-Vista (www.omni-vista.com).
If you are working on anything other than a trivial
system, you should definitely investigate such packages.
Not only will they carry out the calculations for
you, but they will allow you to play “what-if”
simulations to see the effect of adding people to
the project or losing people because of sickness or
other calamities. In addition, they can help accomplish
a more rational form of “negotiation”
with the end-user, in order to examine the results
of various tradeoffs between schedule, manpower, resources,
defects, and risk.

REFERENCES
-
Tom
DeMarco, Controlling Software Projects.
Upper Saddle River, NJ: YOURDON Press/Prentice Hall,
1982.
-
Barry
Boehm, Software Engineering Economics.
Englewood Cliffs, N.J.: Prentice-Hall, 1981.
-
Workshop
on Quantitative Software Models for Reliability,
Complexity, and Cost: An Assessment of the State
of the Art. IEEE Catalog No. TH0067-9.
New York: Institute of Electrical and Electronics
Engineers, 1979.
-
Victor
Basili, Tutorial on Model and Metrics for Software
Management and Engineering. New York: Institute
of Electrical and Electronics Engineers, 1980.
-
C.E.
Walston and C.P. Felix, “A Method of Programming
Measurement and Estimation,” IBM Systems
Journal, Volume 16, Number 1 (January 1977),
pp.54-73.
-
J.W.
Bailey and V.R. Basili, “A Meta-Model for
Software Development and Resource Expenditures,”
Proceedings of the 5th International Conference
on Software Engineering. New York: Institute
of Electrical and Electronic Engineers, 1983.
-
P.V.
Norden, “Useful Tools for Project Management,”
Operations Research in Research and Development.
New York: Wiley, 1963.
-
Larry
Putnam and A. Fitzsimmons, “Estimating Software
Costs,” Datamation, September 1979,
pp. 89-98; October 1979, pp,171-178; November 1979,
pp. 137-140.
-
F.N.
Parr, “An Alternative to the Rayleigh Curve
Model for Software Development Effort,” IEEE
Transactions on Software Engineering, Volume
SE-6, Number 3 (May 1980), pp. 291-296.
-
T.
Capers Jones, Applied Software Measurement,
2nd edition, 1997.
-
Edward
Yourdon, Death March. Upper Saddle River,
NJ: YOURDON Press/Prentice Hall, 1997.
-
Tarek
Abdel-Hamid and Stuart E. Madnick, Software
Project Dynamics: An Integrated Approach. Upper
Saddle River, NJ: Prentice Hall, 1991.

FOOTNOTES
-
Keep
in mind also that the estimates will almost certainly
have to be revised during the project as circumstances
change. External factors (business conditions, new
competitors, mergers, etc.) may cause the user to
change his or her mind about required functionality,
budget expenditures, or required delivery date.
And internal factors (staff turnover, unexpected
difficulty of implementation, etc.) may also cause
budgets and schedules to change, usually dramatically.
-
Some grandmothers
may violently disagree with this assumption!
-
There
is another trade-off, but hardly anyone ever talks
about it explicitly: quality. Many project managers
try to accomplish miracles by delivering all the
required functionality within the user-imposed schedule
and with the less-than-optimal resources provided;
but the inevitable result is a system that has more
bugs and is less maintainable than would otherwise
have been the case.
-
For
an excellent discussion of the “negotiating
games” that take place in many development
projects, see Rob Thomsett, “Double Dummy
Spit, and Other Estimating Games,” American
Programmer, June 1996.
-
One
of the first indications of this was a paper entitled
“Exploratory Experimental Studies Concerning
Online and Offline Programming Performance,”
by H. Sackman, W.J. Erickson, and E. E. Grant in
the January 1968 issue of Communications of
the ACM. Their study showed a 26:1 variation
between the best programmers and the worst programmers,
all of whom were given the same programming task.
This variation between good programmers and bad
programmers has been verified several times during
the past 30+ years.
-
God
is looking over my shoulder as I write this, and
He says, “No, it’s not fine.”
Maybe you’re willing to take the risk of not
being able to deliver the project with the optimistic
schedule and budget that you’re promising,
but a failure is likely to jeopardize much more
than just your career. It’s unethical, unprofessional,
and intellectually dishonest to make unrealistically
optimistic estimates when your boss, your users,
and your entire organization might suffer a considerable
loss by your inability to deliver what you promise.
-
The
term function point was introduced by A.J. Albrecht
to describe this; see “Measuring Application
Development Productivity,” Proceedings of
the Joint SHARE/GUIDE Application Development Symposium
(Chicago: GUIDE International Corp., 1979). Tom
DeMarco uses the term function bang in much the
same way; see his book, Controlling Software
Projects (New York: YOURDON Press, 1982) for
more details. Also, see Capers Jones’ Programming
Productivity (New York: McGraw-Hill, 1986)
for a thorough discussion of the difficulties of
measuring productivity, as well as the many factors
that affect productivity.
-
The exception
to this situation is a consulting firm that charges
its clients for all work, on an hourly basis. The
IT professionals who work for the consulting firm
may not earn any extra pay, but at least the project
manager is likely to have an accurate estimate of
the number of hours actually required to build the
system, and the end-user is likely to have an accurate
picture of the real costs of building the system.
-
A man-millennium
is a thousand man-years of work. I use the term
“man” deliberately, because I am convinced
that women are far too intelligent to get enticed
into estimating in such large, machismo units! The
term “man-millennium” was originally
suggested by one of my company’s clients,
a large public utility company in California.
-
But
it may also be possible to reuse portions of a design
portions of a model of user requirements, or even
portions of a feasibility study. In the past, this
was typically not done because the design model,
analysis models, and feasibility studies were not
well documented and were never maintained. Now,
with the proliferation of analyst workstation products
of the kind discussed in Appendix A, this is becoming
more practical.
-
For
a detailed discussion of this model see Barry Boehm’s
Software Engineering Economics (Englewood
Cliffs, N.J.: Prentice-Hall, 1981).
|
|
|
|