IN THIS CHAPTER,
YOU WILL LEARN:
-
Why the system boundary is arbitrary but critical;
-
How to draw a context diagram for a system;
-
How to produce an event list for a system; and
-
How
to use the context diagram and event list to build
the environmental model.
For
the systems analyst, the most difficult job in specifying
a system is often that of determining what is
part of that system and what is not. Whatever
system you develop, no matter how ambitious, no matter
how grandiose, it will be part of an even larger system.
As we saw in Chapter
2, virtually all systems with which we have human
experience are merely subsystems of even larger systems:
even if our job were to “design the world,”
we would have to recognize that the world is only
a part of the solar system, which is part of a small,
obscure galaxy, which is (ultimately) part of the
universe.
Thus, the first major model that you must develop
as a systems analyst is one that does nothing more
than define the interfaces between the system
and the rest of the universe, that is, the environment.
For obvious reasons, this model is known as the environmental
model. It models the outside of the system;
the model of the inside of the system, known
as the behavioral model, is discussed in Chapters
20 and 21.
In addition to determining what is inside the
system and what is outside the system (which
we accomplish by defining the boundary between
the system and the environment), it is also critically
important to define the interfaces between
the system and the environment. We need to know what
information comes into the system from the external
environment, and we must know what information the
system produces as an output to be delivered to the
external environment.
Of course, inputs and outputs are not produced at
random: no information system gobbles up all available
data from the universe, nor does any realistic system
spew output at random for consumption by the external
environment. The systems we build are rational, purposeful
systems; specifically, they produce outputs as a response
to an event, or a stimulus, in the environment.
Thus, another critical aspect of the environmental
model is that of identifying the events occurring
in the environment to which the system must respond.
Not all events — after all, the environment,
in its totality, generates an infinite number of events!
We are only concerned with those events which (1)
occur in the external environment, and (2) require
a response from the system.
Note that the boundary between a system and its environment,
as illustrated in Figure 18.1, is arbitrary. It may
be made by management decree, or as the result of
political negotiation, or simply by accident. And
it is something that the systems analyst usually has
some opportunity to influence.

Figure
18.1: The boundary between the system and the
environment
Generally,
the user will have a fairly good idea of the general
boundary between the system and the environment. But,
as illustrated in Figure 18.2, there is often a “gray
area” that is open for negotiation, an area
that the user (1) isn’t sure about, (2) hadn’t
thought about, (3) had some preconceived ideas about
which he or she is willing to rethink, or (4) all
the above.
Thus, for example, the user may ask the systems analyst
to develop an accounts receivable system. While this
may represent a well-defined, firm boundary between
the system (known as the A/R system) and the environment,
the systems analyst should certainly consider the
“gray area,” as illustrated by Figure
18.3, of accounts payable, inventory control, cash
management, invoicing, and order entry as a somewhat
larger scope.

Figure
18.2: The gray area between the system and the
environment
If
the systems analyst chooses too small a scope
for a project, he is doomed to failure, for the user
may have unwittingly identified the symptom
of the problem (e.g., “our accounts receivable
are out of control”) rather than the cause
of the problem. And if the systems analyst, through
overconfidence, naivete, or exuberance, chooses too
large a scope for the project, he is doomed to failure,
for he will be dealing with a vastly more complex
political situation, and will be attempting to develop
a system that is probably too large to develop under
any circumstances. And he may be dealing with issues
that the user doesn’t care about or which cannot
be changed at all. Thus, it is important to spend
sufficient time and to get sufficient user concurrence
with the choice of an appropriate system boundary.
In a large system, a number of factors may be taken
into account when the scope of the project is being
chosen. Among the more important factors are these:

Figure
18.3: The gray area surrounding accounts receivable
systems
-
The
user’s desire to achieve a certain share of
the market for the product or to increase it beyond
its current level. This might be done by offering
a new product or increased functionality in an existing
product (e.g., increased functionality offered by
automated teller systems and on-line home banking
systems). Or the user might try to increase market
share by offering a better, faster service to the
marketplace (e.g., “All of our orders are
shipped within 24 hours, and we have a sophisticated
system that tracks your order so we can tell where
it is at all times”).
-
Legislation
enacted by city, state, or federal government(s).
The majority of such systems are reporting systems,
for example, systems that report the employment
(or unemployment) of workers based on age, sex,
nationality, and so on. Or a new system might have
to be built to accommodate changes in the tax laws.
-
A
desire by the user to minimize operational expenses
for some area of his or her business. This was
particularly common when large companies began computerizing
in the 1960s and is true for many small businesses
that are installing their first computer today.
But most organizations that have had computers installed
for ten years or more have already taken advantage
of the obvious opportunities to reduce clerical
overhead.
-
A
desire by the user to gain some strategic advantage
for the product line or business area that he is
operating. The user might attempt to do this
by organizing and managing information about the
marketplace so that he can produce goods in a more
timely and economic fashion. A good example of this
is the airline industry (as well as many other recently
deregulated industries) where better information
about market trends and customer preferences can
lead to more efficient airline schedules and fares.
The
area inside the system boundary is sometimes referred
to as the domain of change. By this, we mean
simply that everything inside the system boundary
is subject to change (e.g., reorganization and/or
automation), while everything outside the boundary
is to be left in its current form and not investigated
by the systems analyst.
To see two examples of system boundaries, examine
the case studies in Appendix
F and Appendix
G. In the case of the YOURDON Press Information
System (Appendix
F), the system boundary is somewhat larger than
one might have expected: it includes invoicing and
handling of cash receipts that would typically be
part of the Accounting Department (and thus outside
the system boundary). Similarly, the elevator controller
in Appendix
G has a boundary somewhat smaller than one might
have wanted: a very different system could have been
developed if the elevator control panels had been
considered part of the system rather than part of
the environment. In both cases, the choices were arbitrary.

18.1 TOOLS USED
TO DEFINE THE ENVIRONMENT
The environmental model consists of three components:
-
Statement
of purpose
-
Context diagram
-
Event list
Each
of these is discussed next.
18.1.1 The Statement of Purpose
The first component of the environmental model is
a brief, concise textual statement of the purpose
of the system. It is intended for top management,
user management, and others who are not directly involved
in the development of the system.
An example of a typical statement of purpose is:
The purpose of the Ajax Book Processing System is
to handle all of the details of customer orders for
books, as well as shipping, invoicing, and back-billing
of customers with overdue invoices. Information about
book orders should be available for other systems,
such as marketing, sales, and accounting.
The statement of purpose can be one, two, or several
sentences long. However, it should not be more than
a single paragraph, as it is not intended to give
a comprehensive, detailed description of the system.
Such an effort would be self-defeating: it is the
purpose of the rest of the environmental model and
the behavioral model to fill in all the details.
As a result, the statement of purpose will be deliberately
vague about many details. In the Ajax example above,
we might ask such questions as:
-
Exactly
what kind of information is provided to accounting,
sales, and marketing by the book order system?
-
How
does the book order system determine whether a customer
is credit worthy? Is this determined by the system
itself or by means of advice from the accounting
department?
-
How
does the system become aware that new books have
been published and are now available for sale?
These
detailed questions can only be answered by looking
at the behavioral model, which we discuss in Chapters
19 and 20.
While the detailed behavioral questions are not answered
by the statement of purpose document, it is generally
sufficient to answer a series of high-level questions:
-
Is the
book order system responsible for payroll activities?
No; virtually anyone reading the material
above would agree that payroll is outside the scope
of the system and is probably included in the accounting
system.
-
Is the
book order system responsible for sending invoices
to customers who order books? Yes; the statement
of purpose says so. One could imagine this to be
a subject of some debate between the book order
department and the accounting department. So, it
is appropriate that it be mentioned in the statement
of purpose.
-
Is
the book order system responsible for inventory
control, that is, for determining when to reorder
books that are about to become out of stock? No.
The statement of purpose makes no such statement.
It is highly conceivable that inventory control
is one of the many other systems (or departments)
that will make use of information about book orders,
as produced by the book order system.
Many systems
analysts also feel that the statement of purpose should
summarize the tangible, quantifiable benefits that
will be achieved by the new system; for example, “the
purpose of the system is to reduce the amount of time
required to process an order from three days to one
day.” While this can be quite useful in small,
highly focused projects, it is not easy to accomplish
on larger projects. Instead, a separate cost-benefit
analysis is usually required.
18.1.2
The Context Diagram
The next part of the environmental model begins to
answer some of the questions raised by the statement
of purpose. The context diagram is a special
case of the dataflow diagram, in which a single bubble
represents the entire system. A context diagram for
the book order system is shown in Figure 18.4. Examples
of context diagrams for two real systems are provided
in Appendices
F and G.
Figure
18.4: A context diagram
The context diagram highlights several important characteristics
of the system:
-
The
people, organizations, or systems with which our
system communicates. These are known as terminators.
-
The
data that our system receives from the outside world
and that must be processed in some way.
-
The
data produced by our system and sent to the outside
world.
-
The
data stores that are shared between our system and
the terminators. These data stores are either created
outside the system and used by our system or created
by our system and used outside the system.
-
The
boundary between our system and the rest of the
world.
Techniques
for constructing the context diagram are discussed
in Section 18.2.
.
18.1.3 The Event List
The event list is a narrative list of the “stimuli”
that occur in the outside world and to which our
system must respond. An event list for the book
order system is shown in Figure 18.5:
-
Customer
places order. (F)
-
Customer cancels order. (F)
-
Management requires sales report. (T)
-
Book reprint order arrives at warehouse. (C)
Figure
18.5: An event list
Note that each event is labeled with either an F,
a T, or a C. This is to show whether the event is
a flow-oriented event, a temporal event,
or a control event. A flow-oriented event is
one associated with a dataflow; that is, the system
becomes aware that the event has occurred when a piece
of data (or possibly several pieces of data) has arrived.
As you can imagine, this will correspond to a dataflow
on the context diagram.
However, not every dataflow on the context diagram
is necessarily a flow-oriented event. Consider, for
example, the partial context diagram shown in Figure
18.6.
Figure
18.6: A partial context diagram
At first glance, one might be tempted to conclude
that dataflows A, B, and C are all indicators of separate,
discrete events. However, it may turn out that only
dataflow A is associated with an event (e.g., the
flow of data is initiated by the terminator). In order
to process the event, it may turn out that the system
explicitly asks other terminators for inputs
along dataflow B and C pursuant to producing some
system response.
Thus, there is not necessarily a one-to-one correspondence
between dataflows on the context diagram and events
in the event list. In general, each dataflow is either
an event (or, more precisely, the indication that
the event has occurred) or is required by the system
in order to process an event.
In addition to flow-oriented events, a system may
also have temporal events. As the name implies,
temporal events are triggered by the arrival of a
point in time. Thus, examples of temporal events might
be the following:
-
A
daily report of all book orders is required at 9:00
AM.
-
Invoices
must be generated at 3:00 PM.
-
Management
reports must be generated once an hour.
Note
that the temporal events are not triggered by incoming
dataflows; one might imagine that the system has an
internal clock with which it can determine the passage
of time. However, keep in mind also that a temporal
event may require the system to ask for inputs from
one or more terminators. Thus, one or more dataflows
may be associated with a temporal event, though the
dataflows, themselves, do not represent the event
itself.
Control events could be considered a special
case of a temporal event: an external stimulus that
occurs at some unpredictable point in time. Unlike
a normal temporal event, the control event is not
associated with the regular passage of time, so the
system cannot anticipate it by using an internal clock.
And unlike a normal flow-oriented event, the control
event does not make its presence known by the arrival
of data. As shown in Figure 18.7, a control event
is associated with a control flow on the context
diagram.

Figure
18.7: A control flow associated with a control
event
The control flow could be regarded as a binary dataflow:
it is either on or off, and it can switch from one
state to the other at any point in time, thereby signaling
the system that it needs to take some immediate
action. Business-oriented information systems typically
have no control flows on their context diagrams; the
YOURDON Press Information System described in Appendix
F, for example, has none. But control flows are
quite common in real-time systems; for an example
of this, look at the context diagram for the elevator
control system in Appendix
G.
18.1.4
Additional Components of the Environmental Model
In most projects, the event list, context diagram,
and statement of purpose are sufficient. However,
two additional components may be useful, depending
on the nature and complexity of the system:
-
Initial
data dictionary, defining external flows and stores
-
Entity-relationship
model of the external stores
Even
a medium-sized system will typically have a few dozen
incoming and outgoing dataflows; a large system may
literally have hundreds. While these dataflows will
eventually be defined in great detail in the behavioral
model (discussed in Chapter
20), it may be useful to begin the construction
of the data dictionary now. This can be important
if the interfaces between the system and the various
terminators are subject to change and negotiation;
the earlier one begins formally defining those interfaces
(by defining the composition and meaning of the stores),
the earlier they can be finalized.
Similarly, an entity-relationship diagram can be constructed
of the external stores (if there are any). This can
help expose relationships between the stores that
otherwise would not become evident until the behavioral
model was being developed. By concentrating on these
relationships at this early stage, we have a way of
double-checking the interactions between the terminators
(who typically include the end users of the system)
and the system itself.
18.2
CONSTRUCTING THE ENVIRONMENTAL MODEL
The discussion above probably makes the environmental
model seem rather simple and straightforward: after
all, there is only one process, a few dataflows and
terminators, a short narrative description of the
system’ s purpose, and a list of events. While
this is true, it often turns out that the environmental
model requires a great deal of work; also, it is usually
developed as a series of iterative refinements, with
additional details being filled in and refined.
One important reason why so many refinements and revisions
are usually necessary is that no one person usually
understands the full scope of the system as it is
initially being defined. If the project involves
a new system that will replace an existing system,
it is possible to talk to the users who are currently
carrying out the system’s functions; in a sense,
they have the perspective of people on the inside
looking out, as illustrated by Figure 18.8. However,
even in this case, the various individual inside users
are generally familiar only with a portion of the
system, and their various views sometimes conflict.
Even worse, your initial interviews with the user
community may omit one or two important users whose
interactions with the terminators outside the system
must be modeled [1].
Figure
18.8: The user’s view of the system
It is important to spend a great deal of time and
energy on the environmental model, for it is often
the focal point of a number of important meetings
and presentations early in the life of a systems development
project. Indeed, it is often the only part of the
overall system model that many high-level users and
managers (the ones with the money to continue funding
the project and the power to cancel the project!)
will ever see. After it has been constructed and approved,
you will find it pinned to several walls and bulletin
boards — so it is important that it be correct.
18.2.1
Constructing the Context Diagram
The context diagram, as we have seen, consists of
terminators, dataflows and control flows, data stores,
and a single process representing the entire system.
We will discuss each in turn next.
The easiest part of the context diagram is the process;
as we have seen, it consists of a single bubble. The
name inside the process is typically the name of the
entire system or an agreed-upon acronym for the system.
Examples are shown in Figure 18.9(a) and (b).
Note that, in the extreme case, the new system may
represent an entire organization; in this case, the
process name would typically be that of the organization
itself, as shown in Figure 18.9(c). [2]
The terminators, as we have seen, are represented
by a rectangular box on the context diagram. Terminators
communicate directly with the system through dataflows
or control flows, as shown in Figure 18.10(a), or
through external data stores, as shown in Figure 18.10(b).
Figure 18.9(a): A typical process name for
a context diagram
Figure
18.9(b): Another typical process name
Figure
18.9(c): A process name representing an entire
organization
Figure
18.10(a): Direct communication between terminator
and system
Figure
18.10(b): Communication through an external store
Note that terminators do not communicate directly
with one another; thus, the context diagram shown
in Figure 18.11 is incorrect. Actually, terminators
do communicate with one another, but since, by definition,
the terminators are external to the system,
the nature and content of any terminator-to-terminator
interactions are irrelevant to the system. If, during
your discussions with the users, you find that it
is essential to know when, why, or how one terminator
communicates with another, then the terminators
are part of the system, and they should be buried
within the process bubble of the context diagram.
Figure
18.11: An incorrect context diagram
Three other points should be made about the terminators:
-
Some
terminators may have a large number of inputs and
outputs. To avoid an unnecessarily cluttered diagram,
it may be convenient to draw the terminator more
than once, as shown in Figure 18.12(a). Note that
the duplicated terminators are marked with an asterisk;
an alternative convention is to represent the duplicated
terminators with a diagonal cross-hatch, as shown
in Figure 18.12(b).
-
When the terminator is an individual person, it
is generally preferable to indicate the role
that the person is playing, rather than indicating
the person’'s identity; thus, Figure 18.13(a)
is preferred over Figure 18.13(b). There are two
reasons for this: first, the person carrying out
the role may change over time, and it is desirable
that the context diagram remain stable and accurate
even if there are personnel changes. And, second,
an individual person may play several different
roles in the system; rather than showing one terminator
labeled “John Smith” with several unrelated
incoming and outgoing flows, it is more meaningful
to show the various roles that John Smith plays,
each as a separate terminator.
-
Because we are primarily interested in developing
an essential model of the system, it is important
to distinguish between sources and handlers
when we draw terminators on the context diagram.
A handler is a mechanism, device, or physical medium
used to transport data into or out of the system.
Because such handlers are often familiar and visible
to users of the current implementation of a system,
there is often a tendency to show the handler, rather
than the true source of data. However, since the
new system will generally have the option of changing
the technology by which data are brought into and
sent out of the system, the handler should not
be shown. Thus, the context diagram shown in Figure
18.14(a) is preferred to the one shown in Figure
18.14(b).
As a compromise,
particularly if the user insists, one can label a
terminator to show both the true source and
the handler that conveys data into or out of the system;
this is illustrated in Figure 18.14(c).
The flows shown on the context diagram model
data coming into the system and data transported out
of the system, as well as control signals received
by the system or generated by the system. Dataflows
are included on the context diagram if they are needed
to detect an event in the environment to which the
system must respond, or if they are needed (as data)
in order to produce a response. Dataflows may also
appear on the context diagram to illustrate data that
are being transported between terminators by the system.
Finally, dataflows are shown on the context diagram
when data are produced by the system to respond to
an event.
As we have already noted, the context diagram of an
essential model avoids (wherever possible) showing
the implementation-oriented handlers that transport
data into and out of the system. Furthermore, we want
to avoid showing the implementation-oriented prompts
and handshaking by which the system and the terminators
tell each other that they are ready for input or output.
Thus, we want to avoid drawing context diagrams like
the one shown in Figure 18.15(a) because it incorporates
implementation assumptions that may be drastically
changed when the new system is implemented.
Figure
18.12(a): Duplicated terminators on the context
diagram

Figure
18.12(b): An alternative way of showing duplicated
terminators

Figure
18.13(a): A preferred way of showing a terminator

Figure
18.13(b): A less preferred way of showing a terminator

Figure
18.14(a): A terminator showing the true source
of data

Figure
18.14(b): A terminator that acts as a handler

Figure
18.14(c): A terminator that combines both source
and handler

Figure
18.15(a): A context diagram with unnecessary
prompts
Instead,
we should draw the context diagram on the assumption
that inputs are caused by and initiated by
the terminators, and that outputs are caused by and
initiated by the system. By avoiding the extraneous
prompts and implementation-oriented inputs and outputs,
we model only the net flow of data.
However, there will be occasions when a terminator
does not initiate input, because, even given perfect
technology, the terminator does not know that the
system requires its input. Similarly, there are occasions
when the system does not initiate the generation of
output, because it does not know that the terminator
needs or wants the output. In both these cases, a
prompt is an essential part of the system,
and it must be shown on the context diagram; an example
is shown in Figure 18.15(b). It is sometimes convenient
to show the prompt and the corresponding input or
output flow with a dialogue flow (a double-headed
arrow), as shown in Figure 18.15(c). [3]
Figure
18.15(b): Dialogue flows to show essential prompts

Figure
18.15(c): An alternative way to show dialogue
flows
18.2.2
Constructing the Event List
The event list, as we have seen, is a simple textual
listing of the events in the environment to which
the system must respond. When building the event list,
make sure that you distinguish between an event and
an event-related flow. For example, the following
is probably not an event:
“Customer order is received by the system.”
Instead, this is probably the incoming dataflow by
which the system becomes aware that the event has
occurred. A more appropriate name for the event might
be
“Customer places order.”
This may seem like an exercise in semantics, but it’s
not. If we describe the event from the system’s
point of view (i.e., from the inside looking out),
we might mistakenly identify incoming flows that are
not events on their own, but that are required
to process some other event. Thus, we always want
to describe the events from the environment’s
point of view (i.e., from the outside looking in).
In most cases, the easiest way to identify the relevant
events for a system is to visualize the system in
action: we examine each terminator and ask ourselves
what effect the terminator’s actions can have
on the system. This is usually done in concert with
the system’s users, who may be playing the role(s)
of the terminators themselves. However, we must be
careful to distinguish between discrete events that
have been accidentally “packaged” together
as if they were a single event; this happens quite
often with flow-oriented events. We must examine the
candidate event and ask ourselves whether all instances
of the event involve the same data; if data are present
in some instances and absent in others, we may actually
have two distinct events. For example, if we look
closely at the event “customer places order,”
we may find that some instances of the event include
the data element “salesperson-ID” and
others do not; and we may find that the system’s
response is different if a salesperson is involved
than if there is no salesperson. Thus, it might be
more appropriate to have two separate events: “customer
places order,” and “salesperson places
customer order.”
Also, keep in mind that the event list must include
not only normal interactions between the system and
its terminators, but also failure mode situations
as well. Since we are creating an essential model,
we do not have to worry about failures of our system;
but we do have to take into account possible failures
or errors caused by the terminators. As Paul Ward
and Stephen Mellor point out in Structured Development
for Real-Time Systems (New York: YOURDON Press,
1985),
Since the terminators are by definition outside the
bounds of the system-building effort represented by
the model, the implementors cannot modify the terminator
technology at will to improve its reliability. Instead,
they must build responses to terminator problems into
the essential model of the system. A useful approach
to modeling responses to terminator problems is to
build a list of “normal” events and then
to ask, for each event, “Does the system need
to respond if this event fails to occur as expected?”
For example, our event list for the Ajax Book Order
System (Figure 18.5) included an event “Book
reprint order arrives at warehouse.” But what
if it does not arrive in a timely fashion (e.g., within
a week of the date promised by the printer)? What
should the system do? We probably need an additional
system-initiated event to cause the system to follow
up with the printer and see why there is a delay.
18.2.3
Which Comes First, the Context Diagram or the Event
List?
You can begin with either the event list or
the context diagram. It really doesn’t matter,
as long as you eventually produce both components
of the environmental model and check to see that
they are consistent with each other.
You may also find yourself talking with people who
are aware of all the things that come into the system
and go out of the system; some users may be able to
provide you with this information, or the maintenance
programmers in charge of maintaining a current version
of the system might be knowledgeable in this area.
This will provide you with the pieces of the context
diagram as a starting point. You can then discuss
the transactions that the users send to the system
and the responses they expect the system to make.
This allows you to create the event list from the
context diagram.
However, you may find yourself in a situation where
the context diagram is not available. This is particularly
common at the beginning of some systems development
projects: it may not be easy to immediately identify
the terminators and the various flows into and out
of the system. In this case, it is often more practical
to begin with an ERD diagram that shows the objects
and relationships. Candidate events can then be
found by looking for activities or operations that
cause instances of a relationship to be created or
deleted. Creation of the event list can then lead
to the development of the context diagram; this is
illustrated in Figure 18.16.
For example, suppose we had identified the objects
CUSTOMER and BOOK in a publishing
system; our user might also tell us that there is
a relationship, “orders,” between CUSTOMER
and BOOK. A likely event, then, would be an
action that creates an instance of the orders relationship;
another event would an action that deletes an instance
of the relationship. This would lead us to identify
“Customer orders book,” and “Customer
cancels book order” as events in our event list.
It should not require too much investigation to realize
that “customer” is a terminator for the
system (while “book” is not); we could
then begin to draw the context diagram.
When we have finished both components of the environmental
model, we should be able to confirm the following:
-
Each
input flow on the context diagram should be needed
by the system to recognize that an event has occurred,
or it should be needed by the system in order to
produce a response to an event, or both.
-
Each
output flow should be a response to an event.
-
Each
nontemporal event on the event list should have
input from which the system can detect that the
event has occurred.
-
Each
event should either produce an immediate output
as its response, or it should store data to be output
later (as a response or part of a response to some
other event), or it should cause the system to change
its state (as indicated on a state-transition diagram).
Figure 18.16: Creation of the context diagram
from an ERD
18.3
SUMMARY
Building the environmental model is the first and
most important part of building a complete model of
user requirements for a new system. At this point,
it may seem like an easy job; after all, the context
diagram consists of only a single bubble, and the
event list looks like a simple list of transactions.
But on a large project, a great deal of work can be
involved: the single bubble in the context diagram
may be interacting with dozens of external terminators
and may have over a hundred incoming and outgoing
dataflows. And the event list is also a major effort
on large systems; there can easily be over a hundred
events that the system has to deal with, and they
all need to be identified. Also, it may be difficult
to come up with an agreed-upon simple statement of
why the system is to exist.
Once you have built the environmental model, it should
be carefully reviewed by all the key user representatives,
as well as by the project team. Then you are ready
to start building the behavioral model, the model
of the inside of the system. This is discussed in
Chapters 19
and 20.

QUESTIONS
AND EXERCISES
-
What are the three things that are defined by the
essential model?
-
What kind of events must be modeled in an essential
model?
-
How is the boundary between the system and the environment
determined by the systems analyst?
-
What is the likely consequence if the systems analyst
chooses too small a scope for the project?
-
What is the likely consequence if the systems analyst
chooses too large a scope for the project?
-
What factors should be taken into account when choosing
the scope for a project?
-
How does the user’s desire to achieve a certain
share of the market affect the scope of a system?
-
How does legislation enacted by various governmental
bodies affect the scope of a system?
-
How does the user’s desire to minimize (or
reduce) operational expenses affect the scope of
a system?
-
How does the user’s desire to gain some strategic
advantage against competition affect the scope of
a project?
-
Research Project: Investigate a project in your
own organization. Which factor do you think was
most influential in choosing the scope? Do you think
the user, the systems analyst, and the project team
were aware of this and were in agreement with it?
-
In general, what do you think are likely to be the
key factors for systems developed in the business
environment of the next decade? For example, will
minimization of operational expenses be more important
than changes caused by government legislation?
-
What are the three major components of the environmental
model?
-
Approximately how long should the statement of purpose
document be?
-
What five characteristics of a system does a context
diagram show?
-
What are the components of a context diagram?
-
What is an event list?
-
What are the three types of events that must be
modeled in a context diagram?
-
What is the relationship between flows and events
on the context diagram?
-
What is a temporal event?
-
What additional components may be found in an environmental
model besides the context diagram, the event list,
and the statement of purpose?
-
Why is it usually necessary to make many revisions
and refinements to the environmental model?
-
Why is it important to ensure that the environmental
model is correct?
-
What kind of name should be put inside the bubble
of a context diagram?
-
What is an enterprise model?
-
How do terminators communicate with the system?
-
Do terminators communicate with each other in a
system model? Why or why not?
-
Under what conditions would a terminator be drawn
more than once on a context diagram? How would it
be shown?
-
If a terminator is an individual person, how should
he or she be shown on the context diagram?
-
How can the systems analyst be sure that he or she
has identified all the terminators in the context
diagram?
-
What is a handler? What is the difference between
a source and a handler?
-
Why should sources rather than handlers be shown
on a context diagram?
-
What should the systems analyst do if the user insists
on showing handlers on a context diagram?
-
Under what conditions are flows shown on a DFD?
-
Why should prompts and handshaking generally not
be shown on a context diagram?
-
What does the term net flow of data mean?
-
Under what conditions does a terminator not initiate
input into a system?
-
Under what conditions does the system not initiate
output to a terminator?
-
Which should be developed first, the context diagram
or the event list? Why?
-
What four things should be checked to ensure that
the environmental model is correct?
-
What is wrong with the following context diagram?
-
What
is wrong with the following context diagram?
-
What is wrong with the following context diagram?
-
What is wrong with the following context diagram?

FOOTNOTES
-
[1]
Such users may not be important in terms of the
organizational hierarchy; they may be regarded as
humble clerks, secretaries, or administrators. Nevertheless,
the functions they perform may be vital,
and it may be crucial to accurately model the inputs
they receive from the external world and the outputs
they send to the outside world. The reason that
the systems analyst often forgets to talk to these
people is very simple: a higher-level user (i.e.,
the boss) will tell the systems analyst who to talk
to. “Don’t bother any of my people,”
the boss will say to the analyst, “they’re
all too busy — that’s why we need the
new system. I’ll tell you everything you need
to know about the system.” As we discussed
in Chapter 3,
there may not be any diplomatic way of avoiding
this; but it is crucial to check the environmental
model carefully to ensure that nothing is missing.
-
[2]
This is an unlikely scenario for a typical systems
development project, but it is beginning to happen
more and more often as people use dataflow diagrams
and other modeling tools described in this book
to build enterprise models. This may be done without
any intention of computerizing the entire enterprise,
but simply to understand what already exists —
especially to understand the data that the organization
needs to carry out its purpose. The subject of enterprise
models is discussed in William Inmon’s Information
Engineering for the Practitioner (Englewood
Cliffs, N.J.: Prentice-Hall, 1987), and James Martin’s
Strategic Data Base Modeling (Englewood
Cliffs, N.J.: Prentice-Hall, 1985).
-
[3]
It’s not required that you use a dialogue
flow, but it does make the context diagram more
readable by packaging the associated input and output
together so they are immediately visible to the
reader. Also, using one arrow to show that the dialogue,
as opposed to two separate arrows, creates a less
cluttered context diagram. This is important on
large systems, where there may be as many as a hundred
or more different interactions with external terminators.
|
|
|
|