“All human
error is impatience, a premature renunciation of method,
a delusive pinning down of a delusion.”
— Franz
Kafka
Letters

IN THIS CHAPTER, YOU WILL LEARN:
-
The concept
of a project life cycle;
-
The
characteristics of the classical project life
cycle;
-
The difference between
classical and semistructured
projects;
-
The components of the
structured life cycle; and
-
The
difference between radical and conservative life cycles.
To be an effective
systems analyst, we
need more than just modeling tools; we need methods. In the systems
development profession, the terms method, methodology, project life cycle,
and systems development life cycle are used almost interchangeably. In Part
III,
we
will look at the detailed methods for doing systems analysis, within the broader
context of a method — known as a structured project life cycle — for
carrying out the overall development of a new system.
Before introducing the
structured project life cycle, it is important to examine the classical project
life cycle
discussed in many textbooks and used in many systems development organizations
today, primarily to identify its limitations and weaknesses. This examination
will be followed by a brief discussion of the semistructured life project
life cycle: a project life cycle that includes some,
but not all, of the elements
of
modern systems development. Next, we introduce the structured project life
cycle, presenting an overview to show the major activities and how they fit
together. Finally, we will examine briefly the iterative, or prototyping,
life cycle introduced in the mid-1980s by Bernard Boar and James Martin, and
now popularized by software engineers such as James Highsmith
and Kent Beck (see (Highsmith, 2000) and (Beck, 2000)).
We will also explore
the concept of
iterative or top-down development. In particular, we will introduce
the notion of radical top-down development and conservative top-down
development. Depending on the nature of a systems development project, there
may be valid reasons for adopting one approach rather than the other; indeed,
some projects may call for a combination of the two.

5.1 THE CONCEPT OF A PROJECT LIFE
CYCLE
As you might expect, small IT
organizations tend to be relatively informal: systems development projects
are begun as the result of a verbal discussion between
the user and the project
manager (who may also be the systems analyst, programmer, computer operator,
and janitor!), and the project proceeds from systems
analysis through design and
implementation without much fuss.
In the larger organizations, however,
things are done on a much more formal basis. The various communications between
users, management, and the project team tend to be documented in writing, and
everyone understands that the project will go through several phases before
it is complete. Even so, it is surprising to see
the major differences between
the way two project managers in the same organization
will conduct their respective
projects. Indeed, it is often left to the discretion of the individual project
manager to determine what phases and activities her or his project will consist
of and how these phases will be
conducted. [1]
Recently,
though, the approach taken to systems development has begun to change.
More and more large and small
organizations are adopting a single, uniform project life cycle — sometimes
known as a project plan or systems development methodology or, simply,
“the way we do things around here.” Usually contained in a notebook
as ponderous as the standards manual that sits (unread) on every analyst’s
and programmer’s desk, the documented project life cycle provides a common way
for
everyone in the systems development organization to go about the business of
developing a computer system.
The approach may be home-grown or,
alternatively, the systems development organization may decide to purchase
a project management package and then tailor it to
company
needs. [2] It seems
apparent that, aside from providing employment for the people who create project
life cycle manuals (and for those who write textbooks about them!), the project
methodology is desirable. What then is the purpose of having a project life
cycle? There are three primary objectives:
-
To define the activities to be
carried out in a systems development project.
-
To introduce consistency among
many
systems development projects in the same organization.
-
To provide checkpoints
for management
control for go/no-go decisions.
The first objective is particularly
important in a large organization in which new people are constantly entering
the ranks of project management. The fledgling project manager may overlook
or underestimate the significance of important
project phases if he or she follows
only intuition. Indeed, it can happen that junior programmers and systems
analysts may not understand where and how their efforts fit into the overall
project unless they are given a proper description of all the phases of
the project.
The second objective is also important
in
a large organization. For higher levels of management, it can be extremely
disconcerting to oversee a hundred different projects, each of which is being
carried out in a different way. For example, if project A defines the systems
analysis activity differently than does project B, and project B doesn’t include
a design phase, how is the second- or third-level manager to know which project
is in trouble and which is proceeding on
schedule? [3]
The third objective of a standard
project life cycle is associated with management’s
need to control a project. On
trivial projects, the sole checkpoint is likely to be the end of the project:
Was it finished on time and within the specified budget? (Or even more simply:
was it finished at all?) And did it accomplish the user's requirements? But
for larger projects, management should have a number
of intermediate checkpoints
during the project, which provide it with opportunities to determine whether
the project is behind schedule, and whether additional
resources need to be
procured. In addition, an intelligent user will also want checkpoints at
several stages in the project so that he can determine whether he wants to
continue funding it! [4]
Having said all this, let me emphasize
that the project life cycle definitely is not in charge of the project. It
will not relieve the project manager of the difficult
responsibility of making
decisions, weighing alternatives, fighting political battles, negotiating with
recalcitrant users, boosting the morale of dejected programmers, or any of
the other project-related trials and tribulations.
The project manager still has to
manage, in every sense of the word. The only help that the project life cycle
can provide is that it can organize the manager’s activities, making it more
likely that the right problems will be addressed at the right time.
5.2 THE CLASSICAL PROJECT LIFE
CYCLE
The kind of project life cycle used in
many organizations today differs from the one to which we’ll be devoting most
of our attention in Part III. The classical, or conventional,
project life cycle
is shown in Figure 5.1. Every project goes through some kind of systems
analysis, design, and implementation, even if it’s not done in exactly the
way shown in the diagram. The project life cycle
used in your organization, for
example, might differ from the one shown in Figure 5.1 in one or all of the
following ways:
-
The survey phase and the
analysis phase may be lumped together into a single phase (this is especially
common in organizations in which anything the user wants is deemed at the
outset to be feasible).
-
There may not be a phase
called hardware study if it can be taken for granted that any new system
can be implemented on an existing computer without causing any major operational
impact.
-
The preliminary design
and detail design phases may be lumped together in a single phase simply
called design.
-
Several of the testing
phases may be grouped together into a single phase; indeed, they may even
be included with coding.
Thus, an individual organization’s
project life cycle may have five phases, or seven phases, or twelve phases,
but it is still likely to be of the classical variety.
What
is it that really characterizes a project life
cycle as being classical? Two features stand out:
a strong
tendency toward bottom-up implementation of the system, and an insistence on
linear, sequential progression from one phase to the next.

Figure 5.1(a): The classical
project life cycle
5.2.1 Bottom-up Implementation
The use
of bottom-up implementation is one of the major weaknesses in the classical
project life cycle. As you can see
from Figure 5.1(a), the programmers are expected to carry out all their module
testing (sometimes known as “component testing”) first, then subsystem
testing, and finally system testing. This approach is also known in the computer
industry as the “waterfall life cycle,” based on a diagram
introduced in (Royce, 1970), and subsequently popularized by Barry Boehm in
(Boehm, 1981). It is shown in Figure 5.1(b).
It’s not clear where this approach
originally came from, but it may have been borrowed from assembly-line
manufacturing industries. The bottom-up implementation approach is a good one
for assembling automobiles on an assembly line, but only after the prototype
model has been thoroughly debugged! [5] Unfortunately,
many system development organizations are still producing one-of-a-kind systems,
for which the bottom-up approach has a number of serious
difficulties:
-
Nothing is done until
it’s
all done. Thus, if the project gets behind
schedule and the deadline falls right in the middle
of system
testing, there
will be nothing to
show
the user except an enormous pile of program listings — which,
taken in their entirety, do nothing of any value for the user!
-
The most trivial bugs are
found at the beginning of the testing period, and the most serious bugs are
found last. This is almost a tautology: Module testing uncovers relatively
simple logic errors inside individual modules; system testing, on the other
hand, uncovers major interface errors between subsystems. The point is
that
major interface errors are not what the programmer wants to find at
the end of a development project; such bugs can lead to the recoding of large
numbers of modules, and can have a devastating impact on the schedule, right
at a time when everyone is likely to be somewhat tired and cranky from having
worked so hard for so many months.
-
Debugging tends to
be extremely difficult during the final stages
of system testing. Note that we distinguish
here between testing and debugging. Debugging is
the black art of discovering where a bug is located (and
the subsequent determination of how to fix the bug) after the
process of testing has determined that there
is a bug. When a bug is discovered during the system-testing
phase of a bottom-up project, it’s often extremely difficult to
tell which module
contains the bug; it could be in any one of the hundreds (or thousands)
of modules that have been combined for the first time. Tracking
down the bug
is often like looking for a needle in a haystack.
-
The
requirement for computer test time usually rises
exponentially during the final stages of
testing. More specifically, the project manager often finds
that she or he needs large contiguous chunks
of computer time for system testing, perhaps
12
hours of uninterrupted computer time per day. Since such a large
amount of computer time is often difficult to
obtain [6], the
project often falls seriously behind
schedule.

Figure 5.1(b): The waterfall
model of systems development
5.2.2 Sequential Progression
The second major weakness with the
classical project life cycle is its insistence that the phases proceed
sequentially from one to the next. There is a natural, human tendency to want
this to be so: We want to be able to say that we have finished the
systems analysis phase and that we’ll never have to worry about that phase
again. Indeed, many organizations formalize this notion with a ritual known
as freezing the specification or freezing the design document.
The only problem
with this desire for
orderly progression is that it’s completely unrealistic! In particular, the
sequential approach doesn’t allow for real-world phenomena having to do with
personnel, company politics, or economics. For example, the person doing the
work, such as the systems analyst or designer, may have made a mistake, and
may have produced a flawed product. Indeed, as human
beings, we rarely do a complex
job right the first time, but we are very good at making repeated improvements
to an imperfect job. Or the person reviewing the work, in particular, the
user who reviews the work of the systems analyst,
may have made a mistake. Or
perhaps the person carrying out the work associated with each phase may not
have enough time to finish, but may be unwilling
to admit that fact. This is a
polite way of saying that, on most complex projects, systems analysis and design
(and system testing, too) finish when someone decides that you have run out
of time, not when you want those activities to finish!
Other
problems are commonly associated with the sequential,
classical project life cycle: During the several
months
(or years) that it takes to develop the system, the user may change his or
her mind about what the system should do. During
the period that it takes to
develop the system, certain aspects of the user’s environment may change (e.g.,
the economy, the competition, or the government regulations that affect the
user’s activities).
An additional characteristic of
the classical project life cycle is that it relies
on outdated techniques. That
is, it tends to make no use of structured design,
structured programming,
walkthroughs, or any of the other modern development
techniques. [7] But
because the classical project life ignores the existence of these
techniques, there is nothing to prevent the project manager from using them.
Unfortunately, many programmers, systems analysts, and first-level project
leaders feel that the project life cycle is a statement of policy by top-level
management; and if management doesn’t say anything about the use of structured
programming, then they, as mere project members and leaders, are not obliged
to use nonclassical approaches.
5.3 THE SEMISTRUCTURED LIFE
CYCLE
The comments in the previous section
make it seem as if most IT organizations are still
living in the Dark Ages. Indeed,
such a characterization is unfair: Not every organization uses the classical
project life. Beginning in the early 1980s, there IT industry began recognizing
that formal, disciplined techniques like structured design, structured
programming, and top-down implementation had some significant benefits. This
recognition has led to the semistructured project life cycle shown in Figure
5.2; it shows two obvious features not present in the classical
approach:
-
The bottom-up sequence of coding,
module testing, and system testing is replaced by top-down implementation,
an approach where high-level modules are coded and
tested first, followed by the
lower-level, detailed modules. There is also a strong indication that
structured programming is to be used as the method of actually coding the
system.
-
Classical design is replaced by
structured design, a formal systems design approach discussed in such books
as (Yourdon and Constantine, 1989) and (Page-Jones,
1988).
Aside from these obvious differences,
there are some subtle points about this modified life cycle. Consider, for
example, that top-down implementation means that some coding and testing are
taking place in parallel. That certainly represents a major departure from
the sequential phases that we saw in the classical
life cycle! In particular, it
can mean feedback between the activity of coding and that of testing
and debugging. When the programmer tests the top-level skeleton version of
the
system, he or she may be heard to mutter, “Jeez, I had no idea that the
double-precision FRAMMIS instruction worked that way!” Naturally,
you can be sure that subsequent use of the double-precision FRAMMIS instruction
will be quite different.
Perhaps more important, the use of
top-down implementation tempts the implementors (and the systems analysts,
if they haven’t abandoned the project by this time)
to talk to the users after the specifications
have been ceremoniously frozen. Thus, it is possible
that the user will point out errors or misunderstandings
in the
specification; the user may even express a desire to change the
specification, and if the conversation takes place directly between the user
and
the implementor, a change may actually be effected before the project manager
knows what is happening. In short, top-down implementation often provides
feedback between the implementation process and the analysis
process — although this feedback exchange is not specifically shown on
Figure 5.2, and although the user and the IT project manager might well deny
that it is taking place!
There is
one final point about the semistructured life cycle: A significant part
of the work that takes place
under the heading of “structured design” is actually a manual effort
to fix up bad narrative specifications. You can see this by looking at Figure
5.3, which depicts the details of structured design. (Note that this figure
consists of the details of process 3 in Figure 5.2.)

Figure 5.2: The semistructured
project life cycle
In Figure
5.3, activity 3.1 (labeled CODIFY FUNCTIONAL SPECIFICATION)
represents a task that designers have long had
to do: translate a monolithic, ambiguous, redundant, narrative document into
a useful, nonprocedural model to serve as the basis
for deriving the hierarchy of
modules that will implement the user’s requirements. In other words, people
practicing structured design have traditionally assumed that they would be
given a classical specification; consequently, their
first job, as they see it, is to
transform that specification into a package of dataflow diagrams, data
dictionaries, entity-relationship diagrams, and process specifications.

Figure 5.3: Details of the
design activity
This is a more difficult job than you
might imagine: Historically, it has been a task carried out in a vacuum.
Designers generally had little contact with the systems analyst who wrote the
long narrative specification, and they certainly had no contact with the
user!
Obviously,
such a situation is ripe for change. Introducing structured analysis — the
kind of modern systems analysis approach presented in this book — into
the picture, as well as expanding on the idea of feedback between one
part of the project and another,
creates an entirely different kind of project life cycle. This is the
structured project life cycle, which we will discuss next.
5.4 THE STRUCTURED PROJECT LIFE
CYCLE
Now that we have seen the classical
project life cycle and the semistructured project life cycle, we are ready
to examine the structured life cycle; it is shown
in Figure 5.4.
We will briefly examine the project
life cycle’s nine activities and three terminators,
as shown in Figure 5.4. The terminators consist of
users, managers, and operations personnel; as you
recall, we discussed their roles in Chapter
3. These are individuals or groups of individuals
who provide input to the project team and who are
the ultimate recipients of the system. They interact
with the nine activities that we have shown in Figure
5.4. Each of the activities is summarized in the following
sections.
5.4.1 ACTIVITY 1: The Survey
This activity is also known as the
feasibility study or initial business study. Typically, it begins when a user
requests that one or more portions of his or her business be automated. The
major purposes of the survey activity are as follows:
-
Identify
the responsible users and develop an initial “scope” of
the system. This may
involve conducting a series of interviews to see which user(s)
are involved in (or affected by) the proposed
project and which are
not. [8]
-
It
may also involve developing an initial context
diagram — a
simple dataflow diagram of the sort shown
in Figure 4.2, in which the entire system is
represented by
a
single
process. [9]
-
Identify current deficiencies
in the user's environment. This will usually consist of a simple narrative
list of functions that are missing or operating unacceptably in the current
system. For example, this might include statements like the following:
-
The hardware for the
current system is unreliable, and the vendor has just gone
bankrupt.
-
The software for the current
system is unmaintainable, and we can no longer hire maintenance programmers
who are willing to maintain software in the programming language used to
develop
the current system.
-
The response time for the
current on-line order entry system is so bad that many customers hang up,
in frustration, before they have entered their order.
-
The
current system is unable to produce the government
reports required by last year’s Tax Reform Act.
-
The current system is
unable to receive credit-limit reports from the accounting department and cannot
produce reports of average order size for the marketing
department.

Figure 5.4: The structured
project life cycle
-
Establish goals and
objectives for a new system. This may also be a simple narrative list
consisting of existing functions that need to be re-implemented, new functions
that need to be added, and performance criteria for the new system.
-
Determine
whether it is feasible to automate the system
and, if so, suggest some acceptable scenarios.
This will involve some very crude and approximate estimates
of the schedule and cost to build a new system and the
benefits to be derived [10];
it will also involve two or more scenarios (e.g., the mainframe
scenario, the distributed processing scenario, etc.).
Though management and
the users will often want a precise, detailed
estimate at this point, the
systems analyst
will be extremely lucky if she or he can estimate the time,
resources, and costs to within ±50% at this early
stage in the project.
-
Prepare
a project charter that will be used to guide
the remainder of the project. The project charter
will include all the information listed above, as well as identify the
responsible
project manager. It may also describe the details of the project life cycle
that the rest of the project will follow.
The survey typically occupies only
5% to 10% of the time and resources of the entire
project, and for small, simple
projects it may not even be a formal activity. However, even though
it may not consume much of the time or resources
of the project, it is a critical activity:
at the end of the survey, management may decide to cancel the project
if it does not appear attractive from a cost-benefit
point of view.
As a systems analyst, you may or may
not
be involved in the survey; the user, together with appropriate levels of
management, may have done it before you even hear about the project. However,
for large, complex projects, the survey involves enough detailed work that
the user will often ask the systems analyst to be
involved as early as
possible.
We will not discuss the survey in any
further detail in this book. If you become involved in this activity, you
may find Appendices E and C useful. For additional
details, consult (Dickinson,
1981), (Gore and Stubbe, 1983), and (Yourdon, 1988).
5.4.2 ACTIVITY 2: Systems
Analysis
The primary purpose of the analysis
activity is to transform its two major inputs, user
policy and project charter, into a structured specification.
This involves modeling the user’s environment
with dataflow diagrams, entity-relationship diagrams,
state-transition diagrams, and the other tools presented
in Chapter 4;
these tools are covered in detail in Part II.
The step-by-step process of systems
analysis (i.e., the subactivities of the analysis
activity in Figure 5.4) is discussed in Part III.
As we will see, it involves the development of an
environmental model (discussed in Chapter
18) and the development of a behavioral model
(discussed in Chapters
19 and 20).
These two models combine to form the essential
model (discussed in Chapter
17), which represents a formal description of
what the new system must do, independent of the nature
of the technology that will be used to implement those
requirements.
In addition to the system model
describing user requirements, a more accurate, detailed
set of budgets and cost-benefit calculations is generally
prepared at the end of the analysis Activity. This
is discussed in more detail in Appendix
C.
Obviously, as a systems
analyst, this is where you will be spending the
major part of your time. There is nothing more
we need to say about the analysis activity at this point, since it is the
subject of the rest of this book.
5.4.3 ACTIVITY 3:
Design
The activity of design is concerned
with allocating portions of the specification (otherwise
known as the essential
model) to appropriate processors (CPUs and/or humans) and to appropriate tasks
(or jobs, or partitions, etc.) within each processor. Within each task, the
design activity is concerned with the development of an appropriate hierarchy
of program modules and interfaces between those modules
to implement the
specification created in activity 2. In addition, the design activity is
concerned with the transformation of entity-relationship data models into a
database design; see (Inmon, 1988) for more details.
Part of this activity will be of
interest to you as a systems analyst: the development
of something called the user implementation model.
This model describes those implementation issues that
the user feels strongly enough about that he or she
is not willing to leave them to the discretion of
the systems designers and programmers. The primary
issues that the user is typically concerned about
is the specification of the human-machine boundary
and the specification of the human interface. The
human-machine boundary separates those parts of the
essential model that are to be carried out by a person
(as a manual activity) from the parts that are to
be implemented on one or more computers. Similarly,
the human interface is a description of the format
and sequence of inputs provided by human users
to the computer (e.g., screen designs and the on-line
dialogue between the user and the computer), as well
as the format and sequence of outputs provided
by the computer to the user. The user implementation
model is described in Chapter
21.
An introduction to the process of systems
design may be found in Chapter
22. Additional material may be found in (Yourdon
and Constantine, 1989), (Page-Jones, 1988), (Jackson,
1975), and others.
5.4.4 ACTIVITY 4:
Implementation
This activity includes both coding
and the integration of modules into a progressively
more complete skeleton of the
ultimate system. Thus, Activity 4 includes both structured programming and
top-down implementation.
As you can imagine, this is typically
an activity that the systems analyst is not involved
with, though there are some projects (and some organizations)
where systems analysis, design, and implementation
are done by the same person. This topic is discussed
in more detail in Chapter
23.
5.4.5 ACTIVITY 5: Acceptance
Test Generation
The structured specification should
contain all the information necessary to define an acceptable system from the
user’s point of view. Thus, once the specification has been generated, work
can commence on the activity of generating a set
of acceptance test cases from the
structured specification.
Since the development of acceptance
tests can take place in parallel with the activities
of design and implementation, it is possible that
you may be assigned to this task after you finish
developing the essential model in Activity 2. Testing
is discussed in more detail in Chapter
23.
5.4.6 ACTIVITY 6: Quality
Assurance
Quality assurance is also known as
final testing or acceptance testing. This activity
requires, as its input, acceptance
test data generated in Activity 5 and an integrated system produced by Activity
4.
The systems analyst could conceivably
be involved in the quality assurance activity, but
typically is not. One or more
members of the user organization may take responsibility, or it may be carried
out by an independent testing group or Quality Assurance Department.
Consequently, we will not discuss the quality assurance function in any further
detail.
Note, by the way, that some people
refer to this activity as quality control rather
than quality assurance. Regardless
of the terminology, we need an activity to verify that the system exhibits
the appropriate level of quality; this is what we
have called quality assurance in
this book. Note also that it is important to carry out quality assurance
activities throughout each of the earlier activities to ensure that
they have been performed at an appropriate level of quality. Thus, one would
expect
a QA activity to be performed throughout the analysis, design, and programming
activity to ensure that the analyst is developing high-quality specifications,
the designer is producing a high-quality design, and the programmer is writing
high-quality code. The quality assurance activity identified here is merely
the final test of the system’s quality.
5.4.7 ACTIVITY 7: Procedure
Description
Throughout
this book, we concern
ourselves with the development of an entire system — not just the automated
portion, but also the portion to be carried out by people. Thus, one of the
important activities to be performed is the generation of a formal description
of those portions of the new system that will be manual, as well as a
description of how the users actually will interact with the automated portion
of the new system. The output of Activity 7 is a user’s
manual.
As you can imagine, this is also an
activity in which you may become involved as a systems analyst. Though we
do not discuss it further in this book, you may wish
to consult books on technical
writing for additional information on the writing of user
manuals.
5.4.8 ACTIVITY 8: Database
Conversion
In some projects, database conversion
involved more work (and more strategic planning) than did the development of
computer programs for the new system; in other cases, there might not have
been any existing database to convert. In the general
case, this activity requires,
as input, the user’s current database, as well as the design specification
produced by Activity 3.
Depending on the nature of the project,
you may or may not become involved in the database conversion activity as a
systems analyst. However, we do not discuss this activity in any greater detail
in this book.
5.4.9 ACTIVITY 9:
Installation
The final
activity, of course, is installation; its inputs are the user’s manual
produced by Actvity 7, the
converted database produced by Activity 8, and the accepted system produced
by Activity 6. In some cases, however, installation
may simply mean an overnight “cutover” to
the new system, with no excitement or fanfare; in other cases, installation
may be a gradual process, as one user group after
another
receives user’s manuals, hardware, and training in the use of the new system
and
actually begin using it.
5.4.10 Summary of the Structured
Project Life Cycle
It’s important
that you view Figure 5.4 for what it is: a dataflow
diagram. It is not a flowchart; there is no
implication that all of activity N must finish before activity N + 1 commences.
On the contrary, the network of dataflows connecting
activities strongly implies
that several activities may be going on in parallel. It is because of this
nonsequential aspect that we use the word activity in the structured project
life cycle, rather than the more conventional word phase. The term phase has
traditionally referred to a particular period of
time in a project when one, and only one, activity was going
on.
There is something else that must
be emphasized about the use of a dataflow diagram
to depict the project life cycle:
A classical dataflow diagram, such as the one in Figure 5.4, does not explicitly
show feedback, nor does it show
control [11].
Virtually every one of the activities in Figure 5.4 can, and usually does,
produce information that can provide suitable modifications to one or more
of the preceding activities. Thus, the activity of design can produce information
that may revise some of the cost-benefit decisions that take place in the
analysis activity; indeed, knowledge gained in the design activity may even
require revising earlier decisions about the basic feasibility of the
project.
Indeed, in the extreme cases, certain
events taking place in any activity could cause the entire project to terminate
abruptly. The input of management is shown only for the analysis activity,
because analysis is the only activity that requires data from management; it
is
assumed, however, that management exerts control over all of the
activities.
In summary, then, Figure 5.4 only
tells us the input(s) required by each activity and
the output(s) produced. The
sequence of activities can be implied only to the extent that the presence
or absence of data makes it possible for an activity
to commence.
5.5 RADICAL VERSUS CONSERVATIVE
TOP-DOWN IMPLEMENTATION
In the previous section, I pointed
out that the structured project life cycle allows
more than one activity to take
place at one time. Let me put it another way: In the most extreme situation,
all the activities in the structured project life cycle could be taking place
simultaneously. At the other extreme, the project manager could decide to
adopt the sequential approach, finishing all of one
activity before commencing on the
next.
It is convenient to have some terminology
to help talk about these extremes, as well as about compromises between the
two extremes. A radical approach to the structured
project life cycle is one in which activities 1 through
9 take place in parallel from the very beginning
of the project; that is, coding begins on the first day of the project, and
the survey and analysis continue until the last day
of the project. By contrast, in
a conservative approach to the structured project life cycle, all of
activity N is completed before activity N + 1 begins.
Obviously, no project
manager in his right mind would adopt either of these two extremes. The key
to recognize is
that the radical and conservative extremes defined above are the two endpoints
in a range of choices; this is illustrated in Figure 5.5. There are an infinite
number of choices between the radical and conservative extremes. A project
manager might decide to finish 75% of the survey activity, followed by
completion of 75% of systems analysis, and then 75% of design, in order to
produce a reasonably complete skeleton version of a system whose details could
then be refined by a second pass through the entire project life cycle. Or,
the manager might decide to finish all the survey and analysis activities,
followed
by completion of 50% of design and 50% of implementation. The possibilities
are
truly endless!

Figure 5.5: Radical and
conservative implementation choices
How does a project manager decide whether
to adopt a radical or conservative approach? Basically, there is no right
answer; the decision is usually based on the following factors:
-
How fickle is the
user?
-
What pressure is the project
team under to produce immediate, tangible results?
-
What pressure is the project
manager under to produce an accurate schedule, budget, and estimate of people
and other resources?
-
What are the dangers of
making a major technical blunder?
As you
can appreciate, not one of these questions has a straight black-or-white
answer. For example, one can’t ask the
user of the system, in casual conversation, “By the way, how fickle
are you feeling today?” On the other hand, the project manager should
be able to assess the situation, based on observation, especially if he
or she
is a
veteran who has dealt with many users and many upper-level managers
before.
If the
project manager judges that he’s
dealing with a fickle user — one whose personality is such that he delays
final decisions until he sees how the system is going to work — then
the manager would probably opt for a more radical approach. The same is true
if
the
manager is dealing with an inexperienced user, who has had very few systems
built for him. Why spend years developing an absolutely perfect set of
specifications only to discover that the user didn’t understand the significance
of the specifications?
If, however, the manager is
dealing with a veteran user who is absolutely sure of what he wants, and
if the user works in
a business area that is stable and unlikely to change radically on a
month-to-month basis, then the project can afford to take a more conservative
approach. Of course, there are a lot of in-between situations: The user may
be
sure of some of the business functions to be performed, but may be
somewhat unsure of the kinds of reports and management information he or she
would like the system to provide. Or, if the user is familiar with batch
computer systems, he or she may be unsure of the impact that an on-line system
will have on the business.
Besides fickleness, there is a second
factor to consider: the pressure to produce immediate, tangible results.
If, due to politics or other external pressures,
the project team simply must get a system
up and running by a specific date, then a somewhat
radical approach is warranted. The project manager
still runs the risk that the system will be
only 90% complete when the deadline arrives, but at least it will be a working 90%
complete skeleton that can be demonstrated and perhaps even put into production.
That’s generally better than having finished all the
systems analysis, all the design, and all the coding, but none of the
testing.
Of course, all projects are
under some pressure for tangible results; it’s simply
a question of degree. And it’s
an issue that can be rather dynamic: A project that begins in a low-key fashion
with a comfortable schedule can suddenly become high-priority, and the deadline
may be advanced six months or a year. One of the advantages of doing the
systems analysis, design, coding, and implementation top-down is that one can
stop an activity at any point and leave the remaining details for subsequent
consideration; meanwhile, the top-level systems analysis that has been completed
can be used to begin the top-level design, and so forth.
Yet another
factor in project management is the ever present requirement, in most
large organizations, to produce
schedules, estimates, budgets, and the like. In some organizations, this tends
to be done in a fairly informal fashion, typically because the projects are
relatively small, and because management feels that any errors in estimating
will have an insignificant impact on the whole organization. In such cases,
one can adopt a radical approach, even though any attempts at estimating
will have
to be “gut-level” guesses. By contrast, most large projects require
relatively detailed estimates of personnel requirements, computer resources,
and so on; and this can only be done after a fairly detailed survey, analysis,
and
design have been completed. In other words, the more detailed and accurate
the estimates have to be, the more likely the project is to follow a conservative
approach.
Finally, the project manager must
consider the danger of making a major technical blunder. For example, suppose
that all his past experience as a project manager has been with small,
one-person Visual Basic projects, which are deployed on a single desktop PC.
And now, all of a sudden, he finds himself in charge of developing an
Internet-based, multiprocessing distributed database e-commerce system that
will process 10 million transactions a day from 50,000
terminals scattered around
the world. In such a situation, one of the dangers of a radical approach
is discovering a major design flaw after a large
portion of the top-level skeleton
system has been implemented.
He may
discover, for example, that in order for his whizbang system to work,
a low-level module has to do its job in
19 microseconds — but his programmers suddenly tell him that there is
no way on earth to code the module that efficiently — not in Java, not
in C, not even in (ugh!) assembly language. So, he must be alert to the fact
that
following the radical approach requires his systems analysts and designers
to pick a “top” to your system relatively early in the game, and
there is always the danger of discovering, down toward the bottom, that they
picked
the wrong top!
However, consider another scenario:
The project manager has decided to build an IT system
with new hardware, a new
operating system, a new database management system (produced by someone other
than the hardware vendor), and a new telecommunications package (produced by
yet another vendor). All the vendors have impressive, glossy manuals describing
their products, but the vendors have never interfaced their respective hardware
and software products together. Who knows if they will work together at all?
Who knows if the throughput promised by one vendor will be destroyed by the
system resources used by one of the other vendors? Certainly, in a case like
this, the project manager might elect a radical approach, so that a skeleton
version of the system could be used to explore possible interface and
interaction problems between the vendors’ components.
If the project manager
is in charge of a familiar kind of system, such
as her 99th payroll system, then she probably has
a very good idea of how realistic her goals are. She probably remembers, from
the last project, what sort of modules she’s going to need at the detailed
level, and she probably remembers very clearly what the top-level system
structure looked like. In such a case, she may be willing to accept the risks
of making a mistake because of the other benefits that the radical approach
will
give her.
In summary, the radical approach is
most suitable for thinly disguised research and development
efforts, where nobody
is quite sure what the final system is supposed
to do. And it is good in
environments in which something must be working on a specific date and
in situations where the user’s perception of what he wants the system to do
is
subject to change. The conservative approach, on the other hand, tends to
be used on larger projects, in which massive amounts of money are being spent
and
for which careful analysis and design are required to prevent subsequent
disasters. However, every project is different and requires its own special
blend of radical and conservative top-down implementation. To deal with the
individual nature of any project, the project manager must be prepared to modify
his approach midstream, if necessary.
5.6 THE PROTOTYPING LIFE
CYCLE
A variation on the top-down approach
discussed above has become popular in quite a few IT organizations. It is
generally known as the prototyping approach and was introduced in the
mid-1980s by Bernard Boar, James Martin, and others. As Boar describes it in
(Boar, 1984):
An alternative approach to requirements
definition is to capture an initial set of needs and to implement quickly those
needs with the stated intent of iteratively expanding and refining them as
mutual user/developer understanding of the system grows. Definition of the
system occurs through gradual and evolutionary discovery as opposed to
omniscient foresight. ... This kind of approach is called prototyping. It
is also referred to as system modeling or heuristic
development. It offers an
attractive and workable alternative to prespecification methods to deal better
with uncertainty, ambiguity, and fickleness of real-world
projects.
In many ways, this sounds exactly like
the radical top-down approach discussed in the section above. The primary
difference is that the structured approach discussed throughout this book
presumes that sooner or later, a complete paper model of the system
will be built (i.e., a complete set of dataflow diagrams, entity-relationship
diagrams, state-transition diagrams, process specifications, etc.). The model
will be completed sooner with a conservative approach and later with a radical
approach; but by the end of the project, there will be a formal set of documents
that should live forever with the system as it undergoes maintenance and
revision.
The prototyping approach, on the other
hand, almost always assumes that the model will be a working model, that is,
a collection of computer programs that will simulate some or all of the functions
that the user wants. But since those computer programs are intended just as
a
model, there is also an assumption that, when the modeling is finished, the
programs will be thrown away and replaced with REAL programs. Prototypers
typically use the following kinds of software tools:
-
An integrated data
dictionary
-
Screen generator
-
Nonprocedural report writer
-
High-level, visual programming
languages [12]
-
Nonprocedural query
language
-
Powerful database management
facilities
The prototyping life cycle proposed by
Boar is shown in Figure 5.6. It begins with a survey activity, similar to that
proposed in this book; this is immediately followed by a determination of
whether the project is a good candidate for a prototyping approach. Good
candidates for a prototyping approach are projects that have the following
characteristics:
-
The user is unable (or
unwilling) to examine abstract paper models like dataflow diagrams.
-
The
user is unable or unwilling to articulate (or “prespecify”)
his or her requirements in any form and can only
determine the requirements through a process of
trial and
error. Or, as my colleague Bob Spurgeon puts it, this is the situation
where the user says, “I don’t know what
I want, but I’ll recognize it when I see it!”
-
The
system is intended to be on-line with full-screen
terminal activities, as opposed to batch edit,
update, and report systems. (Almost all prototyping software tools are
oriented toward the on-line, database-driven, terminal-oriented
approach; there are few
vendor-supplied software tools to help build prototypes of batch
systems.)

Figure 5.6: The prototyping
life cycle
-
The system does not
require specification of large amounts of algorithmic detail, that is, the
writing of many, many process specifications to describe the algorithms by
which output results are created. Thus, decision support, ad hoc retrieval,
and record management systems are good candidates for prototyping. Good candidates
tend to be the systems in which the user is more concerned about the format
and layout of the CRT data entry and output screens and error messages than
about the underlying computations performed by the system.
It is significant
to note that the prototyping life cycle shown in Figure 5.6 concludes
by entering the design
phase of a “traditional” structured life cycle of the sort described
in this book. Specifically, this means that the prototype is not
intended to be an operational system; it is intended solely as a means
of modeling user requirements.
The prototyping approach certainly
has merit in a number of situations. In some cases,
the project manager may want
to
use the prototyping approach as an alternative to the structured analysis
approach described in this book; in other cases, she or he may wish to use
it in conjunction with the development of
paper models such as dataflow diagrams. Keep in mind
the following points:
-
The top-down approach described
in the previous section is another form of prototyping, but instead of using
vendor-supplied tools, such as screen generators and fourth generation
languages,
the project team uses the system itself as its own prototype. That is, the
various versions of a skeleton system provide the working model that the
user
can interact with to get a more realistic feeling of system functions than
he or she might get from a paper model.
-
The prototyping life cycle,
as described above, involves the development of a working model that is then
thrown away and replaced by a production system. There is a significant
danger
that either the user or the development team may try to turn the prototype
itself into a production system. This usually turns out to be a disaster
because
the prototype cannot handle large volumes of transactions efficiently, and
because it lacks such operational details as error recovery, audit trails,
backup/restart facilities, user documentation, and conversion procedures.
-
If
the prototype is indeed thrown away and replaced by the production
system, there
is a real danger that
the project may finish without having a permanent record of user requirements.
This is likely to make maintenance increasingly difficult as time goes
on (i.e., ten years after the system is built, it will be difficult
for maintenance
programmers to incorporate a change, because nobody, including the “second-generation” users
who are now working with the system, will remember what it was supposed
to do in the first place). The life cycle
presented in this book is based on the idea that the paper models developed
in the analysis activity will not only be input to the design activity,
but will
also be retained (and modified, as necessary) during ongoing maintenance.
In fact, the models may survive the system that implements them and serve
as a
specification for the replacement
system.
5.7 SUMMARY
The major purpose of this chapter has
been to provide an overview of project life cycles in general. If you examine
the formal project life cycle in any systems development organization, you
should be able to tell whether it falls into the category of classical,
semistructured, structured, or prototyping.
If your
projects only allow one activity at a time, the discussion
of radical top-down implementation and conservative
top-down implementation in Section 5.6 may have disturbed you. This was my
intent, as the major purpose of that section was to make you think about the possibility of
overlapping some of the major activities in a systems development project. Obviously,
it’s more difficult to manage any project that
has several activities taking place in parallel — but to some extent, that
always happens in every project. Even if the project manager decides that his
or her people will concentrate all their efforts on one major activity at a
time, there will still be a number of subactivities taking place in parallel.
Multiple systems analysts will be interviewing multiple users simultaneously;
various pieces of the final product of systems analysis will be in various
stages of progress throughout the analysis phase. One job of the project
manager is to exercise sufficient control over those subactivities to ensure
that they coordinate smoothly. And in virtually every IT project, this same
kind of parallel activity operated at a higher level, too; that is, despite what
the organization’s formal project life cycle may have recommended, the reality
is that many of the major project activities do overlap to some extent.
Nevertheless, if the project manager decides to insist on a strictly sequential
progression of project activities, the project life cycle presented in this book
will still work.

REFERENCES
-
James A. Highsmith, Adaptive
Software Development: A Collaborative Approach to Managing Complex Systems.
Dorset House, 2000.
-
Kent Beck, eXtreme Programming
eXplained. Addison Wesley, 2000.
-
Edward Yourdon and Larry L.
Constantine, Structured Design: Fundamentals and Applications in Software
Engineering, 2nd ed. Englewood Cliffs, NJ: YOURDON Press,
1989.
-
Meilir Page-Jones, The Practical
Guide to Structured Systems Design, 2nd ed. Englewood Cliffs, NJ: YOURDON
Press, 1988.
-
Bernard Boar, Application
Prototyping. Reading, MA.: Addison-Wesley, 1984.
-
James Grier Miller, Living
Systems. New York: McGraw-Hill, 1978.
-
Edward Yourdon, Managing the
Systems Life Cycle, 2nd ed. Englewood Cliffs, NJ: Prentice-Hall,
1988.
-
Winston
W. Royce, “Managing the
Development of Large Software Systems.” Proceedings, IEEE Wescon,
August 1970; pp. 1-9.
-
Barry Boehm, Software Engineering
Economics. Englewood Cliffs, NJ: Prentice-Hall, 1981.
-
Bill Inmon, Information
Engineering for the Practitioner: Putting Theory into Practice. Englewood
Cliffs, NJ: Prentice-Hall, 1988.
-
Marvin Gore and John Stubbe, Elements
of Systems Analysis,
3rd ed. Dubuque, IA: William Brown, 1983.

QUESTIONS AND
EXERCISES
-
List two synonyms for
methodology.
-
What is the difference between a tool,
as used in this book, and a methodology?
-
What are the three major purposes of
a
project life cycle?
-
Research Project: Find the price of
three commercial methodology products offered by software vendors or consulting
firms.
-
Why do smaller data processing
organizations typically not use formal methodologies?
-
Why is a methodology useful
for new
managers?
-
Why is it important to have a
methodology in an organization with many different projects
underway?
-
Why is a methodology useful for
controlling projects?
-
What are the major distinguishing
characteristics of the classical life cycle?
-
What does bottom-up implementation
mean?
-
What are the four major difficulties
with the bottom-up implementation strategy?
-
What kind of environment is suitable
for a bottom-up implementation approach?
-
Why
does it matter that “nothing is done until it’s all done,” which
characterizes the bottom-up
approach?
-
Why should trivial bugs be found
first in the testing phase of a project?
-
What is the difference between
testing and debugging?
-
Why is debugging difficult in a
bottom-up implementation?
-
What is meant by the phrase
sequential progression when describing a project life cycle?
-
What are the two
major problems with
sequential progression?
-
What are the main differences between
the classical and the semistructured life cycle?
-
What are the two major consequences
of the top-down implementation approach?
-
Why does the design activity in the
semistructured life cycle often involve redundant work?
-
What are the major differences
between the structured and semistructured life cycle?
-
List the nine activities
of the
structured project life cycle.
-
Who are the three types of people who
provide primary input to the project life cycle?
-
What are the five major objectives
of
the survey activity?
-
What is a context
diagram?
-
What is the major purpose of the
analysis activity?
-
What are the types of models produced
by the analysis activity?
-
What is the purpose of the design
activity?
-
What are the two major issues that
the user is typically concerned with in the design activity?
-
When can acceptance
test generation
(Activity 5) begin?
-
What is the purpose of the procedure
description activity?
-
Why has a DFD been used in Figure 5.4
to show the structured project life cycle?
-
What is a possible synonym for
activity?
-
Why is feedback important in the
structured project life cycle?
-
What is the difference between the
radical and conservative approach to the structured project life
cycle?
-
What are the four main criteria for
choosing the radical approach versus the conservative approach?
-
Can you think
of any additional criteria that might be used for
choosing a radical approach versus a
conservative approach?
-
What kind of approach (radical versus
conservative) should a project manager choose if the user is likely to change
his or her mind about the requirements of the system?
-
What kind of approach
(radical versus conservative) should a project
manager choose if the project is under severe
time pressure?
-
What kind of approach (radical versus
conservative) should a project manager choose if the project faces major
technical risks?
-
What is the difference between the
prototyping life cycle and the radical life cycle?
-
What characteristics
does the ideal
prototyping project have?
-
What kind of tools are typically
needed for a prototyping project?
-
Why are batch systems generally not
good candidates for prototyping projects?
-
What are the dangers of the
prototyping approach?
-
How can the prototyping approach and
the structured project life cycle be used together in a
project?

FOOTNOTES
-
[1] This
sounds as if anarchy prevails in most IT organizations;
however, there are two common situations that
lead to this
individualistic approach even
in the most exemplary organization: (1) the highly decentralized organization,
where every department has its own IT group with its own local standards,
and (2) the period of several years immediately
after the last “official
project life cycle” was deemed a failure and thrown out.
-
[2] There
are several such packages on the market, costing
from $10,000 to
$100,000 or more; the larger “Big-5” accounting firms, and major IT consulting
organizations have developed proprietary versions of such packages, which they
sometimes sell together with consulting services and automated tool-support.
I
won’t comment on any specific project management package; I will only suggest
that you keep the concepts presented in this book in mind if your organizations
uses a vendor-supplied package.
-
[3] Miller
points out in (Miller, 1978) that this is a commonly observed phenomenon;
indeed, he presents it as a general “hypothesis” applicable
to all living systems:
“HYPOTHESIS 2-1: System components
incapable of associating, or lacking experience which has formed such
associations, must function according to rigid programming or highly
standardized operating rules. It follows that as turnover of components
rises above the rate at which the components can develop the associations
necessary
for operation, rigidity of programming increases.”
-
[4] In
fact, the politics of most IT development projects
are such that there is only one checkpoint at which
the user has an obvious, clean way of backing
out: at the end of the survey, or feasibility study, phase. In theory, though,
the user should have the opportunity to cancel an IT project at the end of
any phase if he thinks he is wasting money.
-
[5] Many
people feel that the bottom-up approach may also
have come from the computer hardware industry, because
many of the early computer programmers and
programming managers in the 1950s and 1960s were electrical engineers who had
previously been involved in the development of hardware.
-
[6] I’m
convinced that yet another of the Murphy-type laws
applies in this regard: The larger and more critical
the project, the more likely it is that its
deadline will coincide with end-of-year processing and other organizational
crises that gobble up all available computer time!
-
[7]
We will summarize these modern development techniques
in Chapter 7.
-
[8]
Interviewing techniques are discussed in Appendix
E.
-
[9]
The context diagram is part of the environmental
model that we will discuss in detail in Chapter
18. Its major purpose, as indicated here, is
to define the scope of the system (what is in the
system and what is out of the system), as well as
the various terminators (people, organizational
units, other computer systems, etc.) with whom the
system will interact.
-
[10]
Cost-benefit calculations are discussed in Appendix
C.
-
[11]
Actually, there are ways of showing feedback and
control in dataflow diagrams, as we will see in
Chapter 9.
The additional notations (for control processes
and control flows) are normally used for modeling
real-time systems, and we have avoided their use
in this model of the “system for building
systems.”
-
[12]
In Chapter
23, we refer to these as “5th generation”
languages, to distinguish them from the older 4th
generation languages which provided very high-level
capabilities, but still required programmers to
use “line-at-a-time” text editors to
create the programs. Examples of visual development
environments are Microsoft’s Visual Basic
and Visual C++; IBM’s Visual Age for Smalltalk
and its visual COBOL development environment; and
most vendor-supplied versions of Java.
|
|
|
|